scholarly journals Bi-Directional Static Load Tests of Pile Models

2020 ◽  
Vol 10 (16) ◽  
pp. 5492
Author(s):  
Michał Baca ◽  
Włodzimierz Brząkała ◽  
Jarosław Rybak

This work examined a new method of bi-directional static load testing for piles, referencing the Osterberg test. Measurements were taken, on a laboratory scale, using six models of piles driven into a box filled with sand. This method allowed for separate measurements of pile base and pile shaft bearing capacities. Based on the results, the total pile bearing capacity and equivalent Q–s diagrams were estimated. The results obtained show that the structure of the equivalent curve according to Osterberg is a good approximation of the standard Q–s curve obtained from load tests, except for loads close to the limit of bearing capacity (those estimates are also complicated by the inapplicability and ambiguity of a definition of the notion of limit bearing capacity); the equivalent pile capacity in the Osterberg method represents, on average, about 80% of the capacity from standard tests.

2015 ◽  
Vol 36 (2) ◽  
pp. 45-49 ◽  
Author(s):  
Zygmunt Meyer

Abstract Statistic load test is the most commonly used method for estimation of the bearing capacity of piles. From the test we obtain the series a values: load-settlement, Q–s curve. In practice, it is extremely difficult to reach the critical load of the pile when the settlement turns out of control. The existing methods that allow bearing capacity to be calculated give the value which is very often 1/10 of the critical load. The question arises if it is possible based upon short series of load, i.e., 0–0.4 critical load, to predict the critical value of the load, with accuracy which is sufficient for practical calculation. The paper presents a method how to calculate the critical load based upon short series of load in the static load tests.


Author(s):  
Brent Phares ◽  
Yoon-Si Lee ◽  
Travis K. Hosteng ◽  
Jim Nelson

This paper presents a laboratory investigation on the performance of grouted rebar couplers with the connection details similar to those utilized on the precast concrete elements of the Keg Creek Bridge on US 6 in Iowa. The testing program consisted of a series of static load tests, a fatigue test, and evaluation of the chloride penetration resistance of laboratory specimens. The goal of this testing was to evaluate the ability of the grouted rebar couplers to develop flexural capacity at the joint between the precast elements as well as the durability of the connection. For structural load testing, seven full-scale specimens, each with #14 epoxy-coated rebars spliced by epoxy-coated grouted couplers, were fabricated and tested in three different loading cases: four-point bending, axial tension plus bending, and a cyclic test of the system in bending. The static load testing demonstrated that the applied axial load had a minimal effect on the formation of cracks and overall performance of the connection. When ultra-high performance concrete was used as a bedding grout, the initiation of crack was slightly delayed but no considerable improvement was observed in the magnitude of the crack width during loading or the crack closure on unloading. The results of the seventh specimen, tested in fatigue to 1 million cycles, showed little global displacement and crack width throughout the test, neither of which expanded measurably. No evidence of moisture or chloride penetration was detected at the grouted joint during the 6-month monitoring.


Author(s):  
Kevin N. Flynn ◽  
Bryan A. McCabe

Driven cast-in-situ (DCIS) piles are classified as large displacement piles. However, the use of an oversized driving shoe introduces additional complexities influencing shaft resistance mobilisation, over and above those applicable to preformed displacement piles. Therefore, several design codes restrict the magnitude of shaft resistance in DCIS pile design. In this paper, a series of dynamic load tests was performed on the temporary steel driving tubes during DCIS pile installation at three UK sites. The instrumented piles were subsequently subjected to maintained compression load tests to failure. The mobilised shear stresses inferred from the dynamic tests during driving were two to five times smaller than those on the as-constructed piles during maintained load testing. This was attributed to soil loosening along the tube shaft arising from the oversized base shoe. Nevertheless, the radial stress reductions appear to be reversible by the freshly-cast concrete fluid pressures which provide lower-bound estimates of radial total stress inferred from the measured shear stresses during static loading. This recovery in shaft resistance is not recognised in some European design practices, resulting in conservative design lengths. Whilst the shaft resistance of DCIS piles was underpredicted by the dynamic load tests, reasonable estimates of base resistance were obtained.


2018 ◽  
Vol 45 (10) ◽  
pp. 889-898 ◽  
Author(s):  
Daniel Pickel ◽  
Susan Tighe ◽  
Warren Lee ◽  
Rico Fung

The Ministry of Transportation of Ontario was interested in a rehabilitation strategy that could be used to address deep-seated rutting issues encountered on its 400-series highways. A precast concrete inlay panel (PCIP) rehabilitation design was developed and constructed involving the installation of precast panels into partially-milled asphalt pavement. Sub-surface instrumentation was installed at the PCIP–asphalt interface including earth pressure cells and moisture sensors installed in six instrumentation clusters. This instrumentation has been monitored to gather information regarding the PCIP trial installation. Readings from the moisture sensors indicate that water penetrates beneath the PCIPs in precipitation events, though these moisture levels recede under dry conditions, indicating that the water can exit the sub-slab area. Static load testing using a fully-loaded gravel truck was used to determine the different support reactions caused by different loading configurations. Higher loads were generally found beneath the joints in the two loading situations studied.


2011 ◽  
Vol 243-249 ◽  
pp. 4402-4407
Author(s):  
Yong Hong Miao ◽  
Guo Jun Cai ◽  
Song Yu Liu

Six methods to determine axial pile capacity directly based on piezocone penetration test (CPTU) data are presented and evaluated. Analyses and evaluation were conducted on three types piles that were failed during pile load testing. The CPT methods, as well as the CPTU methods, were used to estimate the load carrying capacities of the investigated piles (Qp ). Pile load test were used to determine the measured load carrying capacities (Qm). The pile capacities determined using the different methods were compared with the measured pile capacities obtained from the pile load tests. Two criteria were selected as bases of evaluation: the best fit line for Qp versus Qm and the arithmetic mean and standard deviation for the ratio Qp /Qm. Results of the analyses showed that the best methods for determining pile capacity are the CPTU methods.


2001 ◽  
Vol 78 (7) ◽  
pp. 518-524 ◽  
Author(s):  
MOHAMADOU LAMINE DIALLO ◽  
PIERRE SIMONET ◽  
BENOIT FRENETTE ◽  
BERNARD SANSCHAGRIN

Author(s):  
Moncef Souissi

The capacity-to-torque ratio, Kt, has been used in the design of helical piles and anchors for over half a century. Numerous research efforts have been conducted to accurately predict this capaci-ty-to-torque ratio. However, almost of all these Kt factors are based on shaft geometry alone. The ca-pacity-to-torque ratio described herein was found to depend on the shaft diameter, shaft geometry, helix configuration, axial load direction, and installation torque. In this study, 799 full scale static load tests in compression and tension were conducted on helical piles of varying shaft diameters, shaft geometry, and helix configurations in different soil types (sand, clay, and weathered bedrock). The collected data were used to study the effect of these variables on the capacity-to-torque ratio and resulted in developing a more reliable capacity-to-torque ratio, Km, that considers the effect of the variables mentioned above. The study shows that the published Kt values in AC358 (ICC-ES Acceptance Criteria for Helical Piles Systems and Devices) underestimate the pile capacity at low torque and overestimate it at high torque. In addition, and based on probability analysis, the predicted capacity using the modified Km results in a higher degree of accuracy than the one based on the published Kt values in AC358.


2019 ◽  
Vol 2019 ◽  
pp. 1-12 ◽  
Author(s):  
Zhijun Zhou ◽  
Yaqin Dong ◽  
Peijun Jiang ◽  
Dandan Han ◽  
Tong Liu

In this paper, a static load test and a multiparameter statistical analysis method are used to study the value of pile side friction in different soil layers in a loess region. Currently, static load testing is the most commonly used method to determine the bearing capacity of pile foundation. During the test, a vertical load is applied at the top of the pile, the data under each load level are recorded, and a Q-S curve is drawn to obtain the ultimate bearing capacity of a single pile. Reinforcement stress gauges are installed at different sections of the pile body, and then the axial force and the pile side friction of each section are calculated. Few studies have investigated the calculation of pile side friction in different soil layers using the multiparameter statistical analysis method. Obtaining accurate results using this method will provide an important supplement to the calculation of pile side friction and will also be conducive to the development of theoretical calculation of pile side friction. Therefore, taking Wuding Expressway project in loess region as an example, the lateral friction resistance of six test piles is studied through static load testing and multiparameter statistical analysis. The multiparameter statistical analysis method is compared with the static load test results, and the error is controlled within 20%. The results show that the calculation results of multiparameter statistical analysis essentially fulfill engineering requirements.


2017 ◽  
Vol 2017 ◽  
pp. 1-11 ◽  
Author(s):  
Jialin Zhou ◽  
Xin Zhang ◽  
Hongsheng Jiang ◽  
Chunhao Lyu ◽  
Erwin Oh

This paper examines shaft and base grouted concrete piles by conducting vertical static load tests (SLTs) and dynamic load tests. Three concrete piles with shaft and base grouting, with base grouting only, and without grouting techniques were selected, and compressive SLTs were conducted. Two piles with grouting were also assessed with dynamic load tests. Another two uplift SLTs were conducted to one shaft and base grouted pile and one pile without grouting. Traditional presentations were provided to check whether the bored piles reached the design requirement. Interpretations of test results were also provided to determine the ultimate pile capacity. Results from these 5 SLT programs indicated that double-tangent and DeBeer's methods are close to each other, and Chin's method overestimates the pile capacity. Comparison of the results from the SLTs and dynamic load tests shows that the results from Chin's method are close to dynamic results, and Mazurkiewicz's method overestimates for friction resistance. The results also demonstrate that base and shaft grouted pile and base grouted pile increase by 9.82% and 2.89% in compressive capacity, respectively, and compared to the uplift SLTs; there is a 15.7% increment in pile capacity after using base and shaft grouting technology.


Sign in / Sign up

Export Citation Format

Share Document