Delivering Russia's Longest Offshore ERD Open-Hole Gravel Pack Well

2017 ◽  
Author(s):  
Manish Kumar ◽  
Vincent Bouches ◽  
Alexander Shmakov ◽  
Alexey Plotnikov
Keyword(s):  
2021 ◽  
Author(s):  
Seng Wei Jong ◽  
Yee Tzen Yong ◽  
Yusri Azizan ◽  
Richard Hampson ◽  
Rudzaifi Adizamri Hj Abd Rani ◽  
...  

Abstract Production decline caused by sand ingress was observed on 2 offshore oil wells in Brunei waters. Both wells were completed with a sub-horizontal openhole gravel pack and were subsequently shut in as the produced sand would likely cause damage to the surface facilities. In an offshore environment with limited workspace, crane capacity and wells with low reservoir pressures, it was decided to intervene the wells using a catenary coiled tubing (CT) vessel. The intervention required was to clean out the sand build up in the wells and install thru-tubing (TT) sand screens along the entire gravel packed screen section. Nitrified clean out was necessary due to low reservoir pressures while using a specialized jetting nozzle to optimize turbulence and lift along the deviated section. In addition, a knockout pot was utilized to filter and accommodate the large quantity of sand returned. The long sections of screens required could not be accommodated inside the PCE stack resulting in the need for the operation to be conducted as an open hole deployment using nippleless plug and fluid weight as well control barrier. A portable modular crane was also installed to assist the deployment of long screen sections prior to RIH with CT. Further challenges that needed to be addressed were the emergency measures. As the operation was to be conducted using the catenary system, the requirement for an emergency disconnect between the vessel and platform during the long cleanout operations and open hole deployment needed to be considered as a necessary contingency. Additional shear seal BOPs, and emergency deployment bars were also prepared to ensure that the operation could be conducted safely and successfully.


2007 ◽  
Author(s):  
Kevin S. Whaley ◽  
Colin John Price-Smith ◽  
Allan Jeffery Twynam ◽  
Phillip John Jackson

2016 ◽  
Author(s):  
I. Martinez-Zuazo ◽  
M. Fernandez ◽  
A. Medina ◽  
C. J. Segnini-Rodriguez ◽  
J. Atienza ◽  
...  

2013 ◽  
Author(s):  
Yoliandri Susilo ◽  
Kevin Whaley ◽  
Santiago Loboguerrero ◽  
Phillip Jackson ◽  
Natig Kerimov ◽  
...  
Keyword(s):  

2016 ◽  
Author(s):  
Vadim V. Salyaev ◽  
Suleyman S. Sitdikov ◽  
Andrey M. Nuykin ◽  
Georgiy G. Arzamastsev ◽  
Pavel S. Pilgun ◽  
...  

Geofluids ◽  
2021 ◽  
Vol 2021 ◽  
pp. 1-9
Author(s):  
Fei Xu ◽  
Shengtian Zhou ◽  
Chong Zhang ◽  
Yi Yu ◽  
Zhao Dong

Shunted screen gravel packing is a kind of technology which is difficult to complete gravel packing with the conventional method in low fracture pressure formation and long wellbore length condition. According to the characteristics of LS 17-2 deepwater gas field, the shunted screen packing tool was designed and the gravel packing process and packing mechanism were analyzed. The variation law of the flow friction, flow rate distribution in multichannel, and other parameters of the shunted screen gravel packing were analyzed and calculated. The friction calculation model of different stages of gravel packing was established. A gravel packing simulation software was developed to simulate the friction in different stages of shunted screen gravel packing. The parameters such as sand-dune ratio, pumping sand amount, packing length, and packing time in the process of packing were also calculated. In deepwater horizontal well gravel packing, the results show that the friction ratio of the string is the largest in the stage of injection and α-wave packing. While the friction increases rapidly in the stage of β-wave packing because the carrier fluid needs to flow through the long and narrow washpipe/screen annulus. Particularly when the β-wave packing is near the beginning of the open hole, the packing pressure reaches the maximum. The calculated results are in good agreement with the measured results of the downhole pressure gauge. The model and software can provide technical support for the prediction and optimization of gravel packing parameters in the future.


2021 ◽  
Author(s):  
Kevin Whaley ◽  
Phillip J Jackson ◽  
Michael Wolanski ◽  
Tural Aliyev ◽  
Gumru Muradova ◽  
...  

Abstract Open Hole Gravel Pack (OHGP) completions have been the primary completion type for production wells in the Azeri-Chirag-Gunashli (ACG) field in Azerbaijan for 20 years. In recent years, it has been required to use well bore strengthening mud systems to allow drilling the more depleted parts of the field. This paper describes the major engineering effort that was undertaken to develop systems and techniques that would allow the successful installation of OHGP completions in this environment. OHGP completions have evolved over the last 3 decades, significantly increasing the window of suitable installation environments such that if a well could be drilled it could, in most cases, be completed as an OHGP if desired. Drilling fluids technology has also advanced to allow the drilling of highly depleted reservoirs with the development of well bore strengthening mud systems which use oversized solids in the mud system to prevent fracture propagation. This paper describes laboratory testing and development of well construction procedures to allow OHGPs to be successfully installed in wells drilled with well bore strengthening mud systems. Laboratory testing results showed that low levels of formation damage could be achieved in OHGPs using well bore strengthening mud systems that are comparable to those drilled with conventional mud systems. These drilling fluid formulations along with the rigorous mud conditioning and well clean-up practices that were developed were first implemented in mid-2019 and have now been used in 6 OHGP wells. All 6 wells showed that suitable levels of drilling mud cleanliness could be achieved with limited additional time added to the well construction process and operations and all of them have robust sand control reliability and technical limit skins. Historically it was thought that productive, reliable OHGP completions could not be delivered when using well bore strengthening mud systems due to the inability to effectively produce back filter cakes with large solids through the gravel pack and the ability to condition the mud system to allow sand screen deployment without plugging occurring. The engineering work and field results presented demonstrate that these hurdles can be overcome through appropriate fluid designs and well construction practices.


2021 ◽  
Author(s):  
Chih-Cheng Lin ◽  
Andrew G. Tallin ◽  
Xueyong Guan ◽  
Jiten D. Kaura ◽  
Sasha F. Luces ◽  
...  

Abstract One of the major technical challenges to this project was placing horizontal open hole gravel packs (HzOHGP) within the narrow pore pressure to frac-gradient (PPFG) margin in the target reservoirs. This paper addresses the steps taken to overcome this challenge. To maximize the use of the narrow PPFG margin, the project combined a managed pressure drilling (MPD) system with low gravel placement pump rates made possible by an ultra-light-weight proppant (ULWP).  Of the MPD systems available, the Controlled Mud Level (CML) system was selected over the Surface Back Pressure (SBP) system for several reasons. It enabled conventional gravel pack pumping operations and equipment and it accommodated the brine weight needed to inhibit the shales. A series of lab tests showed that the completion fluid density required to inhibit the reservoir shale reactivity was only possible using CML. An overall evaluation of CML showed that it was most suitable and offered the greatest flexibility for the gravel pack job design. The special ceramic ULWP had to be qualified and tested.  The qualification testing ranged from standard API and compatibility tests to full scale flow loop testing. The flow loop tests were needed to measure the ULWP transport velocity for the target wellbore geometry. Understanding the transport velocity is critical for gravel pack design and job execution planning. Once MPD and ceramic ULWP were selected, the gravel pack placement operations were simulated to demonstrate that their features increased the likelihood of successfully gravel packing in the target reservoirs.  Small PPFG margins decrease the probability of success of placing a HzOHGP.  In the target formations, the pressure margin is insufficient to safely execute HzOHGP conventionally; instead, the project combined MPD and the low pump rates facilitated by using ULWP to control circulating pressures to stay inside the narrow margin and place the gravel packs. The integration of CML and ULWP into in a gravel pack operation to control circulating pressures has never been done. The concept and its successful field implementation are industry firsts.


Sign in / Sign up

Export Citation Format

Share Document