Effect Of Artificial Islands on Structural Integrity Management of Existing Offshore Platforms: Case Study

2012 ◽  
Author(s):  
Abdul Gaffur Varikkodan
Author(s):  
Mohamed A. El-Reedy

The GUPCO offshore structure management system was developed as a part of an integrated infrastructure management system. This paper presents a case study of providing an integrity management system for inspection, evaluation and repair of the fixed offshore platforms in Gulf of Suez. The management system procedure is presented focusing on the first step for defining the highly risky weight to the lower risky weight structure based on API criteria for assessment of the existing structures. The risk analysis methodology for developing design and assessment criteria for fixed offshore structure based on consequence of failure is illustrated. In our case study the assessment method is applied for a number of fixed offshore structures. The above methodology is performed after theoretical assessment and then verifying by using ROV subsea inspection for the fixed offshore structure. Comparison between the actual structure performance and the predicting risk assessment for the structure from the model will be studied. The overall management system will be illustrated in scope of predictive maintenance philosophy and reliability for all offshore structures.


2010 ◽  
Author(s):  
Samuel Defranco ◽  
Patrick O'Connor ◽  
Frank Puskar ◽  
Justin R. Bucknell ◽  
Kris A. Digre

2017 ◽  
Vol 862 ◽  
pp. 265-270
Author(s):  
Raditya Danu Riyanto ◽  
Murdjito

Offshore structure, particularly fixed offshore structures, should be kept in the performance for the fit-for-purpose condition during their operating lifetime. For fixed offshore structures that exceed their designated life years, the proper Structural Integrity Management System (SIMS) should be developed and applied. Despite the fixed offshore platforms have their service life, there are still platforms that continue to operate exceeding their service lifetime. These ageing platforms should be taken care thoroughly to avoid the consequences that could take casualties. This paper will propose the proper initiation of SIMS development for ageing fixed offshore platforms in Indonesia, by taking an example at Bekapai Field Platforms in East Kalimantan. Using HAZID technique and several ranking criteria, the platforms are assessed and ranked. Platforms that categorized in critical condition are grouped based on similarities in geometry and function. The highest rank is analyzed in computer Finite Element Analysis (FEA) Software with modification based on latest inspection result. This method is proven to be a proper method to be used as a maintenance program for ageing fixed offshore platforms in Indonesia.


Author(s):  
O. O. Ajayi

Integrity Management of pipeline structures and offshore platforms is of great concern in the oil industry to prevent failure and damage which can result in ecological and environmental pollution. This paper presents the experience of a multinational oil company in the coast of West Africa. It will focus on how integrity management is used as a proactive measure to prevent corrosion and damage to offshore platforms. The paper will focus on planning, implementation and management of the integrity management strategy in the company. The case study described in this paper will focus on the best practices and lessons learnt from other companies operating in the region.


Author(s):  
Jon Freddy Hernández Sánchez ◽  
Carlos Antonio Vergara ◽  
Carlos Hidalgo

Colombia is a country located in a geographical area with great geological diversity, where every day the effects of climate change increases the probability of the failure of buried pipelines due to the movement of land or the instability associated with them. That is why the use of geometric In Line Inspection (ILI) intelligent tools with the inertial module is important for the diagnosis of structural integrity of pipelines and is associated with an integrity management program due to the geotechnical threats present throughout its path. It decreases maintenance costs due to pump stoppage for unscheduled repairs, anticipating the solution, and mitigating and controlling deformations in the pipeline caused by geotechnical ground displacements. OCENSA-Pipeline Central SA (Colombia) has developed, through its experience, a program to manage integrity by determining the structural expense in specific sections due to displacement of the pipeline caused by ground movement through the use of the Geometric ILI tools and MFL inertial module. This paper specifically presents the use of the tool in decision-making based on OCENSA’s preset study limits for deformations in the elastic range and plastic building material of the pipeline. In 1997 OCENSA was among the first companies in Latin America to use Inertial Geo-positioning technology; today there are sectors which have been inspected with this technology as many as five times, in which pipe displacement of up to 5 meters has been found. The case study presented refers to a geographical point on the route of the pipeline located in the Andes, at the site of the movement known as the “La negra” ravine, near the town of Puente Nacional, where movements of the pipeline associated with geotechnically unstable slope conditions were detected by In line inspection (ILI) Geometric and inertial modules, beginning in 2004. Since that time, integrity management was conducted in order to reduce the chances pipeline failure will materialize in this area of geotechnical instability.


Author(s):  
Hamid Golpour ◽  
Mostafa Zeinoddini ◽  
Hadi Khalili ◽  
Ali Golbaz ◽  
Yashar Yaghubi ◽  
...  

The existing knowledge on the structural integrity assessment of offshore platforms may benefit from case studies on the life extension evaluations of aging structures. This paper presents a case study for the structural integrity assessment of an existing 8 legged aging drilling platform located in the Persian Gulf. The platform is now 42 years old and the objective of the study is to check its fit for purpose for a life extension of 25 years beyond 2012. The structural model is based on the best estimates of the existing conditions of the platform. A number of analysis approach such as i) assessment based on the previous exposures, ii) linear (elastic), iii) equivalent linear (or the linear global analysis with local overload considerations), and iv) non-linear analysis methods have been used to estimate the structural integrity of the platform. The paper provides further background, clarifications and proposed updates to API-RP 2A-Section 17. The paper is divided into three parts. Section 1 is a discussion on the background of the previous assessment study and perspective view on why the case study platform needs to be assessed. Section 2 and Section 3 include the finding of the code-noncompliance points of the platform based on the recommendations of API RP 2A-2007. Section 4 presents the remedy actions recommended for the fit for purpose of the platform.


Author(s):  
Mehrdad Kimiaei ◽  
Jalal Mirzadeh ◽  
Partha Dev ◽  
Mike Efthymiou ◽  
Riaz Khan

Abstract Fixed offshore platforms subject to wave-in-deck loading have historically encountered challenges in meeting target reliability levels. This has often resulted in costly subsea remediation, impacted platform occupancy levels or premature decommissioning of critical structural assets due to safety concerns. This paper addresses the long-standing industry challenge by presenting a novel structural reliability approach that involves converging the analytical behavior of a structure to its measured dynamic response for assessment. In this approach, called the Structural Integrity Management (SIM) TRIAD method, the platform model is calibrated based on the measured in-field platform natural frequencies using a structural health monitoring (SHM) system, so that the reliability assessment can be performed on a structural model whose stiffness is simulated as close to reality as possible. The methodology demonstrates the potential of unlocking structural capacity of offshore structures by removing conservatism normally associated with traditional reliability assessment methods, thus significantly improving the ability to achieve target structural reliability levels in a cost effective manner. The SIM TRIAD method has been implemented while assessing an existing fixed offshore platform subject to wave-in-deck loads, which is located in East Malaysian waters. It has enabled the facility operator to achieve acceptable target structural reliability and has assisted in developing an optimized risk-based inspection (RBI) plan for ensuring safe operations to end of asset field life. The methodology and findings of the assessment are presented in this paper to illustrate the benefits of the SIM TRIAD method.


2013 ◽  
Author(s):  
Roberto Piva ◽  
Margherita Latronico ◽  
Andrea Nero ◽  
Stefano Sartirana