Factors influencing formwork productivity
Estimates indicate that 30 to 70 percent of cast-in-place concrete cost is attributable to the assembly and stripping of formwork. This wide percentage range is partially due to factors that are not well understood with regard to their influence on productivity. The purpose of this paper is to identify the factors that influence formwork productivity and identify a methodology to evaluate productivity data. Two groups of factors were found to have a great effect on formwork productivity: non-measurable factors such as contract document and measurable factors such as engineering design. This paper discusses the effect of both groups of factors on the productivity of vertical formwork. To quantify the effect of the measurable factors on formwork productivity, a case study of the productivity of a crew of carpenters erecting wall formwork for a three-story underground parking structure is presented and analyzed. Data were collected by physically measuring the daily output of vertical formwork erected and the total daily work hours. Key words: formwork, productivity, construction methods.