Monitoring and Control System in an Area of Geotechnical Risk Unstable in the Camisea Gas Transport System

Author(s):  
Fernando A. Velásquez Martinez ◽  
Carlos Romero Acero

The experience gained during the operation and maintenance activities on the Camisea Pipeline Gas Transport System (SDT) owned by TGP in Peru — which goes from the Amazon rainforest in the region of Cusco to the Pacific coast near Lima, along 729 Km — has led to the evolution and the optimization of the design, construction and maintenance processes regarding works focused on the stabilization of the slopes along the right of way of the pipeline carrying natural gas and natural gas liquid. This section of the right of way is 95 km long and crosses tropical mountains in the Amazon rainforest, in a transitional area between the Manugaly valley and the basin top boundary. It was noticed since 2005 that the right of way had being affected by a land slide consisting of a horizontal crack in the ground, between both pipelines and along them. So, after number of in-site inspections, the team concluded that the area was being affected by a large ground removal event. As a consequence, traces of geotechnical instability were found on the right side of the right of way, consisting of stress cracks, transverse settlements and leaks. All of those were affecting the stability conditions of the ground. From the annual in-site follow-up, monitoring and geotechnical testing, the team established that this process affecting the right of way was caused by a large mass removal process directly related to the increase of the imbalance rate of an old colluvial deposit below the entire area, triggered by the heavy rainfall in the area — ca. 3 500 mm a year, mainly between October and April. It is to be mentioned that the axis of the NG and NGL pipelines is located on the top of this colluvial deposit, which is susceptible to landslides. This is noticeable because of cracks present in the place. Local geomorphology and heavy deforestation — caused by locals — triggers an increase of the rainfall water filtration rate into the ground, thus speeding up the slide processes. Piezometers installed in the area showed high levels of the local water table. Movement readings are: top length: 70 m; length: 250 m; width: 150 m. Criteria for the construction of landslide mitigation structures in the pipeline área are being established based on a permanent land survey monitoring system — including inclinometers, piezometers and strain-gages — as this is a large regional movement. This control action allowed the operation to continue free of damages to the pipelines and under controlled costs.

2013 ◽  
Vol 24 (2) ◽  
pp. 83-97 ◽  
Author(s):  
Cristian Eparu ◽  
Renata Rădulescu ◽  
Doru Stoica

AbstractThe natural gas consumption of the operators connected to the gas transport system depends on the gas needs. As gas needs vary in time, the whole process of gas transportation is, therefore, nonstationary. The paper presents nonstationary simulations for a gas transportation network and highlights the parameters values (flows, pressures) that are necessary to assure the safety of the system.


Author(s):  
Francisco Oliveros ◽  
John Malpartida ◽  
Alberto Melo ◽  
Christian Rosario ◽  
Marcos Mecatti

Abstract Camisea Pipeline Transportation System (PTS) in Peru, owned by Transportadora de Gas del Perú (TGP) and operated by Compañía Operadora de Gas (COGA), begins in the Amazon rainforest, crosses the Andes Mountains (4850msnm) and finally descends towards the Pacific coast. The PTS has been operating for more than 10 years and it has Natural Gas (NG) and Natural Gas Liquids (NGL) transportation pipelines. The NG pipeline is 888km long which includes two Loops (105km and 18km in the coast and mountain sectors, respectively). NGL pipeline is 557km long. From the beginning (0 km) to 210 km, the Right of Way (RoW) is located in the geotechnical context of the Amazon rainforest. Then, between km 210 and km 420, the PTS crosses the mountain chain of the Andes. Finally, between km 420 and Km 730 the RoW is located on the Peruvian Pacific coast. TGP’s operation of the PTS identifies, analyzes and controls the different types of threats that can affect the integrity of the pipelines. The operation is developed according to international standards defined in the Pipeline Integrity Management (PIM) of the operation. Consequently, hazards such as Third Party Damage (TPD), geohazard, external and internal corrosion, among others, are analyzed. However, associated to the economic growth and development of Peru, there have been some cases where the intervention of a person, community or industrial activity in the surroundings of the RoW has resulted in the level of geohazards are spontaneously modified and activated. Consequently, the degree of stability of the RoW is necessary to analyze the integrity of the NG and NGL pipelines. This article describes the occurrence of some practical cases where there was a change in the stability of the RoW of the TGP’s PTS triggered by activities related to TPD. It is highlighted that the identification, analysis, definition and execution of mitigation actions are carried out in a transversal way which involves the participation of different operational areas such as: Integral Maintenance, Geotechnics, Integrity, Social Management, among others. All the activities are done with the approach of keeping the balance between community, environment and infrastructure. Some of the cases considered are: Flood and scour of the RoW triggered by the failure of a water tank in an industrial area, scour of channels due the obstructions and an unstable slope process generated by constructions near the RoW. Today, the operation develops activities in order to mitigate geohazards generated by TPD. Some of these activities are, among others: Social awareness, technical talks, agreements with industrial and local administration entities, geotechnical maintenance and monitoring. In addition, it is highlighted that all the mentioned mitigation actions are carried out in a transversal manner between different operational areas. Afterward, the collected information is properly saved in the Geographic Information System database.


Author(s):  
Francisco Oliveros ◽  
Emilio Hernández ◽  
Guillermo Soto

The Camisea’s Pipeline Transportation System (PTS) in Peru, owned by Transportadora de Gas del Perú (TgP) and operated by Compañía Operadora de Gas del Amazonas (COGA), stars in the Amazon rainforest, crosses the Andes Mountain (4850masl) and descends finally towards the coast of the Pacific. The PTS has more than 10 years of operation and it has two pipelines: one transports Natural Gas (NG) and the other Natural Gas Liquids (NGL) pipelines. The NG pipeline has a length of 864km including a Loop pipeline of 135km. The NGL pipeline has a length of 557km. Because of particular physiographic conditions of each geographic sector that cross the right-of-way (ROW), the integrity of the PTS acquires a level of significant susceptibility to the occurrence of geohazard, which are the product of natural erosive processes and mass movements. In the coast sector, one of the most representative processes of geotechnical instability is the soil or debris flow (mass movements of soils). The occurrence of this type of flow has a greater incidence in the torrential creek, which generate transport of large volumes of sediments during rainy seasons. The flow has destructive effects and therefore, it is necessary to analyze the geomorphological, geological and hydrological aspects of the main creek and rivers that crosses the ROW with the objective of maintaining the integrity of the pipelines. In Peru, the flows are associated and known as Huayco or Huaico. As an additional component, it is highlight that the Peruvian coast is located within the area of interaction between the South American Continental Plate and the Nazca Plate, where there is evidence of seismic activity with different magnitude that influence on the occurrence of geo-dynamic processes with certain periods of frequency that could change the terrane’s morphology. The current article describes technical aspects of identification, intervention, monitoring, and geotechnical control in sub-fluvial crossings with levels of potential damage to the geohazard defined as huayco in the integrity management program of PTS. This activity include 63 main sub-fluvial crosses, approximately 30% are of the seasonal flow regime, located in the coast zone; at the same time, these are tributary to main rivers of constant flow as is the case of the Pisco, Cañete and Mala rivers. In this paper, it is place a special emphasis on the fourth crossing of the Huáncano creek, because it is a place of potential impact in the occurrence of soil flows. Within the annual geotechnical maintenance of the sub-fluvial crosses, in the part of the Peruvian coast, for the operation of the PTS of TgP, bed and banks protection some works are implemented, such as: Check dams, re-channeling, levees and stone riprap (Stone armour). Likewise, a program of evaluation and technical inspection is develop: it includes the analysis of the expected levels of undermining and performance condition of the existing works, which allow defining the geotechnical intervention in a term according to the identified risk level. All in all framed within a process of permanent geotechnical monitoring of the right of way. Finally, it is highlighted that to date the application of the process described above has been continued, which has facilitated the development and continuous assessment of the risk condition by huaycos in the PTS of TgP. This program has maintained an operation with an acceptable level of risk in the areas of interest and avoiding problems and consequences of great impact to communities, the environment and the operation of the system.


Author(s):  
Nataliia Kharytonova ◽  
Olha Mykolaienko ◽  
Tetyana Lozova

Greening of roads contributes to the protection of roads and their elements from influence of adverse weather and climatic factors; it includes the measures for improvement and landscaping of roads, ensures the protection of roadside areas from transport pollution, provides visual orientation of drivers. The solution of these issues will ensure creation and maintenance of safe and comfortable conditions for travelers. Green plantings in the right-of-way road area include woody, bushy, flower and grass vegetation of natural and artificial origin. For proper operation of public roads and satisfaction of other needs of the industry, there may be the need in removing the greenery. The reason for the removal of greenery in the right-of-way road area may be due to the following factors: construction of the architectural object, widening of the motor road, repair works in the security zone of overhead power lines, water supply, drainage, heating, telecommunications facilities, cutting of hazardous, dry and fautal trees, as well as self-grown and brushwood trees with a root neck diameter not exceeding 5 cm, elimination of the consequences of natural disasters and emergencies. The removal of plantations in the right-of-way area is executed in order to ensure traffic safety conditions and to improve the quality of plantations composition and their protective properties. Nowadays, in Ukraine there is no clear procedure for issuing permits for removing of such plantations. In order to resolve this issue, there is a need in determining the list of regulations in the area of forest resources of Ukraine and, if needed, the list of regulatory acts that have to be improved; to prepare a draft of the regulatory legal act that would establish the procedure of plantations cutting, the methodology of their condition determination, recovery costs determination, the features of cutting. Keywords: plantations, cutting, right-of-way, woodcutting permit, order.


2019 ◽  
Vol 12 (12) ◽  
pp. e231320
Author(s):  
Mário José Pereira-Lourenço ◽  
Duarte Vieira-Brito ◽  
João Pedro Peralta ◽  
Noémia Castelo-Branco

This case report describes the case of a 37-year-old man that noticed an intrascrotal right mass with 1 month of evolution. During physical exam presented with a large mass at the inferior portion of the right testicle, clearly separated from the testicle, with a tender consistency and mobile. An ultrasound was performed that showed a solid and subcutaneous nodular lesion, extra testicular, heterogeneous, measuring 7.2 cm. Pelvic magnetic resonance imageMRI showed a lesion compatible with a lipoma. The patient was subjected to surgical excision of the lesion by scrotal access, having histology revealed a lipoblastoma (LB) of the scrotum. Histological diagnosis was obtained by microscopic characteristics (well-circumscribed fatty neoplasm) and immunohistochemistry (stains for CD34, S100 protein and PLAG1 were positive; stains for MDM2 and CDK4 were negative). LB is extremely rare after adolescence in any location, being this first described case of intrascrotal LB described in adulthood.


2021 ◽  
Vol 16 (1) ◽  
Author(s):  
Lubna Bakr ◽  
Hussam AlKhalaf ◽  
Ahmad Takriti

Abstract Background Primary cardiac tumours are extremely rare. Most of them are benign. Sarcomas account for 95% of the malignant tumours. Prognosis of primary cardiac angiosarcoma remains poor. Complete surgical resection is oftentimes hampered when there is extensive tumour involvement into important cardiac apparatus. We report a case of cardiac angiosarcoma of the right atrium and ventricle, infiltrating the right atrioventricular junction and tricuspid valve. Case presentation Initially, a 22-year-old man presented with dyspnoea. One year later, he had recurrent pericardial effusion. Afterwards, echocardiography revealed a large mass in the right atrium, expanding from the roof of the right atrium to the tricuspid valve. The mass was causing compression on the tricuspid valve, and another mass was seen in the right ventricle. Complete resection of the tumour was impossible. The mass was resected with the biggest possible margins. The right atrium was reconstructed using heterologous pericardium. The patient’s postoperative course was uneventful. Postoperative echocardiography showed a small mass remaining in the right side of the heart. Histopathology and immunohistochemistry confirmed the diagnosis of angiosarcoma. The patient underwent adjuvant chemotherapy and radiotherapy later on. He survived for 1 year and 5 days after the surgery. After a diagnosis of lung and brain metastases, he ended up on mechanical ventilation for 48 h and died. Conclusions Surgical resection combined with postoperative chemotherapy and radiotherapy is feasible even in patients with an advanced stage of cardiac angiosarcoma when it is impossible to perform complete surgical resection.


1985 ◽  
Vol 61 (1) ◽  
pp. 222-222
Author(s):  
John Trinkaus
Keyword(s):  

2014 ◽  
Vol 525 ◽  
pp. 227-231 ◽  
Author(s):  
Min Xiao ◽  
Chun Long Feng

In order to solve the problem of Diesel natural gas dual fuel engine, such as power reduction, low charging efficiency, the conception of diesel engine fueled with pilot-ignited directly-injected liquefied natural gas is put forward. On the basis of this theory, a medium speed diesel of the marine is refitted into dual fuel engine, in order to keep original power, decrease the temperature of combustion and reduce emission. The LNG injection timing, duration of LNG injection and the different ratios the pilot diesel to total energy are studied the method of AVL FIRE software. Conclusions are as follows: When the different ratios pilot diesel to total energy is 0.5%, the engine can not work; Delaying the LNG injection timing, shortening the LNG injection duration and choose the right ratios pilot diesel to total energy can reach the indicated power of original machine, and the NOx emissions level will be greatly reduced.


Sign in / Sign up

Export Citation Format

Share Document