Ukraine’s First Large-Scale CFB 200 MWe Anthracite Fired Starobeshevo Power Plant

Author(s):  
Victor A. Shevtchenko ◽  
Werner Franke ◽  
Peter Gummel ◽  
Marian Kotrus ◽  
George von Wedel

JSC Donbassenergo, a major utility in the Ukraine, is operating power plants of approx. 3500 MW, mostly operated with their local fuel anthracite. As the existing facilities are reaching their age a strategy has been developed to apply state-of-the-art technology for revamping. On this basis the decision has been taken to replace boiler No. 4 of the Starobeshevo Power Plant with a boiler based on CFB technology. The unit is designed for 670 t/h of superheated and 538 t/h of reheated steam with 545 / 543 °C and 13.2 / 2.5 MPa temperature and pressure to account for the existing steam turbine which generates 200 MW electricity. Fuels used are a local anthracite and anthracite sludge left from coal washing and which is available in large quantities. Emissions are designed in accordance with European regulations allowing 200 mg/m3 (STP) for NOX and 200 mg/m3 (STP) for SO2. A basic description of the overall plant will be given. Details on the design of the CFB boiler which is equipped with Lurgi’s patented pant-leg and other design issues will be explained. Operating results from the commissioning and first commercial operation will be presented.

Author(s):  
Rainer Quinkertz ◽  
Thomas Thiemann ◽  
Kai Gierse

High efficiency and flexible operation continue to be the major requirements for power generation because of the benefits of reduced emissions and reduced fuel consumption, i.e. reduced operating costs. Ultra super critical (USC) steam parameters are the basis for state of the art technology of coal fired power plants with highest efficiency. An important part of the development process for advanced steam turbines is product validation. This step involves more than just providing evidence of customer guaranteed values (e.g. heat rate or electric output). It also involves proving that the design targets have been achieved and that the operational experience is fed back to designers to further develop the design criteria and enable the next step in the development of highly sophisticated products. What makes product validation for large size power plant steam turbines especially challenging is the fact that, due to the high costs of the required infrastructure, steam turbine manufacturers usually do not have a full scope / full scale testing facility. Therefore, good customer relations are the key to successful validation. This paper describes an extensive validation program for a modern state of the art ultra supercritical steam turbine performed at an operating 1000 MW steam power plant in China. Several measuring points in addition to the standard operating measurements were installed at one of the high pressure turbines to record the temperature distribution, e.g. to verify the functionality of the internal cooling system, which is an advanced design feature of the installed modern high pressure steam turbines. Predicted 3D temperature distributions are compared to the actual measurements in order to verify and evaluate the design rules and the design philosophy applied. Conclusions are drawn regarding the performance of modern 3D design tools applied in the current design process and an outlook is given on the future potential of modern USC turbines.


2016 ◽  
Vol 839 ◽  
pp. 44-48
Author(s):  
Phairot Phanukan ◽  
Nipon Ketjoy

This article presents the availability of 4 large scale grid connected photovoltaic (PV) power plants that located in Petchaboon, Nakhon Sawan, and Chai Nat province of Thailand. These power plant size are 4.5 MW and 6.5 MW. In addition, they are constructed with the same platform, component, and commercial operation date (COD) in the same year. The data were collected during 1st August 2012 to 31st October 2014. The study result found that availability of these power plant is over 97 % every year except Nakhon Sawan 1 plant in the first year. The internal unavailability trend is quickly reduce while external unavailability is randomly fluctuation.


Author(s):  
Junichi Koike ◽  
Shinobu Nakamura ◽  
Hajime Watanabe ◽  
Tsuyoshi Imaizumi

Pressurized Fluidized Bed Combustion Combined Cycle Power Generation, namely, PFBC is the clean coal technology, utilizing gas turbine and steam turbine, which is high efficient and friendly to earth. In early 90’s, 70 MW class PFBCs had started demonstration and commercial operation all over the world. Kyushu Electric Power Company (KyEPCO) decided to apply this technology as the real commercial unit, the world largest capacity 360MW, and put into commercial operation in July 2001. To apply PFBC to the large-scale commercial plant, it is essential to demonstrate the higher efficiency than any other conventional coal firing units. In order to achieve this, the gas turbine with higher operation pressure and advanced supercritical steam condition for steam turbine were applied. The reduction by size and weight of the equipment is the vital must to realize large scale PFBC, as 360MW unit. To reduce the pressure vessel size, the unique design of hexagon furnace was applied to install it efficiently in smaller vessel. The plant has started commercial operation in July 2001 and has well demonstrated PFBC’s technology advantages as planned. It achieved the efficiency, 41.8% as net value based on HHV, which is the highest level among existing coal fired power plants. It also verifies smooth operation, 3%L/min of Load following capability, 3 hours of hot start-up, that is comparable to conventional pulverized coal fired unit.


Atmosphere ◽  
2021 ◽  
Vol 12 (7) ◽  
pp. 811
Author(s):  
Yaqin Hu ◽  
Yusheng Shi

The concentration of atmospheric carbon dioxide (CO2) has increased rapidly worldwide, aggravating the global greenhouse effect, and coal-fired power plants are one of the biggest contributors of greenhouse gas emissions in China. However, efficient methods that can quantify CO2 emissions from individual coal-fired power plants with high accuracy are needed. In this study, we estimated the CO2 emissions of large-scale coal-fired power plants using Orbiting Carbon Observatory-2 (OCO-2) satellite data based on remote sensing inversions and bottom-up methods. First, we mapped the distribution of coal-fired power plants, displaying the total installed capacity, and identified two appropriate targets, the Waigaoqiao and Qinbei power plants in Shanghai and Henan, respectively. Then, an improved Gaussian plume model method was applied for CO2 emission estimations, with input parameters including the geographic coordinates of point sources, wind vectors from the atmospheric reanalysis of the global climate, and OCO-2 observations. The application of the Gaussian model was improved by using wind data with higher temporal and spatial resolutions, employing the physically based unit conversion method, and interpolating OCO-2 observations into different resolutions. Consequently, CO2 emissions were estimated to be 23.06 ± 2.82 (95% CI) Mt/yr using the Gaussian model and 16.28 Mt/yr using the bottom-up method for the Waigaoqiao Power Plant, and 14.58 ± 3.37 (95% CI) and 14.08 Mt/yr for the Qinbei Power Plant, respectively. These estimates were compared with three standard databases for validation: the Carbon Monitoring for Action database, the China coal-fired Power Plant Emissions Database, and the Carbon Brief database. The comparison found that previous emission inventories spanning different time frames might have overestimated the CO2 emissions of one of two Chinese power plants on the two days that the measurements were made. Our study contributes to quantifying CO2 emissions from point sources and helps in advancing satellite-based monitoring techniques of emission sources in the future; this helps in reducing errors due to human intervention in bottom-up statistical methods.


Author(s):  
V. A. Khrustalev ◽  
M. V. Garievskii

The article presents the technique of an estimation of efficiency of use of potential heat output of an auxiliary boiler (AB) to improve electric capacity and manoeuvrability of a steam turbine unit of a power unit of a nuclear power plant (NPP) equipped with a water-cooled water-moderated power reactor (WWER). An analysis of the technical characteristics of the AB of Balakovo NPP (of Saratov oblast) was carried out and hydrocarbon deposits near the NPP were determined. It is shown that in WWER nuclear power plants in Russia, auxiliary boilers are mainly used only until the normal operation after start-up whereas auxiliary boiler equipment is maintained in cold standby mode and does not participate in the generation process at power plants. The results of research aimed to improve the systems of regulation and power management of power units; general principles of increasing the efficiency of production, transmission and distribution of electric energy, as well as the issues of attracting the potential of energy technology sources of industrial enterprises to provide load schedules have been analyzed. The possibility of using the power complex NPP and the AB as a single object of regulation is substantiated. The authors’ priority scheme-parametric developments on the possibility of using the thermal power of the auxiliary boilers to increase the power of the steam turbine of a nuclear power plant unit equipped with WWER reactors unit during peak periods, as well as the enthalpy balance method for calculating heat flows, were applied. The surface area of the additional heater of the regeneration “deaerator – high pressure heaters” system and its cost were calculated. On the basis of calculations, it was shown that the additional power that can be obtained in the steam turbine of the NPP with a capacity of 1200 MW due to the use of heat of the modernized auxiliary boiler in the additional heat exchanger is 40.5 MW. The additional costs for the implementation of the heat recovery scheme of the auxiliary boiler at different prices for gas fuel and the resulting system effect were estimated in an enlarged way. Calculations have shown the acceptability of the payback period of the proposed modernization.


Author(s):  
Erik Rosado Tamariz ◽  
Norberto Pe´rez Rodri´guez ◽  
Rafael Garci´a Illescas

In order to evaluate the performance of new turbo gas power plants for putting in commercial operation, it was necessary to supervise, test and, if so the case, to approve the works of commissioning, operational and acceptance of all equipments and systems that constitute the power plant. All this was done with the aim of guaranteeing the satisfactory operation of these elements to accomplish the function for which they were developed. These activities were conducted at the request of the customer to confirm and observe that the evidence of the tests was carried out according to the specifications and international regulations. The putting into commercial operation activities were done in collaboration with the supplier and manufacturer of equipment, the client and the institution responsible for certification and approval of the plant. All this in a logical and chronological order for the sequence of commissioning tests, operation and acceptance. Commissioning tests were carried out on-site at normal operating conditions, according to the design and operation needs of each power plant of a group of 14. Once the commissioning tests were completely executed and in a satisfactory manner, operational tests of the plants were developed. This was done by considering that they must operate reliable, stable, safe and automatically, satisfying at least, one hundred hours of continuous operation at full load. After evaluating the operational capacity of the machine, it was necessary to determinate the quality of the plant by carrying out a performance test. Finally, it was verified if every unit fulfills the technical requirements established in terms of heat capacity of the machine, noise levels and emissions. As a result of this process, it is guaranteed to the customer that the turbo gas power plants, their systems and equipments, satisfy the requirements, specifications and conditions in agreement with the supplier and manufacturers referring to the putting into commercial operation of the plant.


Author(s):  
Dennis Toebben ◽  
Tobias Burgard ◽  
Sebastian Berg ◽  
Manfred Wirsum ◽  
Liu Pei ◽  
...  

Abstract Combined cycle power plants (CCPP) have many advantages compared to other fossil power plants: high efficiency, flexible operation, compact design, high potential for combined heat and power (CHP) applications and fewer emissions. However, fuel costs are relatively high compared to coal. Nevertheless, major qualities such as high operation flexibility and low emissions distinctly increase in relevance in the future, due to rising power generation from renewable energy sources. An accelerated start-up procedure of CCPPs increases the flexibility and reduces the NOx-emissions, which are relatively high in gas turbine low load operation. Such low load operation is required during a cold start of a CCPP in order to heat up the steam turbine. Thus, a warm-keeping of the thermal-limiting steam turbine results in an accelerated start-up times as well as reduced NOx-emissions and lifetime consumption. This paper presents a theoretical analysis of the potential of steam turbine warm-keeping by means of hot air for a typical CCPP, located in China. In this method, the hot air passes through the steam turbine while the power plant is shut off which enables hot start conditions at any time. In order to investigate an improved start-up procedure, a physical based simplified model of the water-steam cycle is developed on the basis of an operation data set. This model is used to simulate an improved power plant start-up, in which the steam turbine remains hot after at least 120 hours outage. The results show a start-up time reduction of approximately two-thirds in comparison to a conventional cold start. Furthermore, the potential of steam turbine warm-keeping is discussed with regards to the power output, NOx-emissions, start-up costs and lifetime consumption.


2019 ◽  
Vol 122 ◽  
pp. 02004 ◽  
Author(s):  
Javier Menéndez ◽  
Jorge Loredo

In 2017, electricity generation from renewable sources contributed more than one quarter (30.7%) to total EU-28 gross electricity consumption. Wind power is for the first time the most important source, followed closely by hydro power. The growth in electricity from photovoltaic energy has been dramatic, rising from just 3.8 TWh in 2007, reaching a level of 119.5 TWh in 2017. Over this period, the contribution of photovoltaic energy to all electricity generated in the EU-28 from renewable energy sources increased from 0.7% to 12.3%. During this period the investment cost of a photovoltaic power plant has decreased considerably. Fundamentally, the cost of solar panels and inverters has decreased by more than 50%. The solar photovoltaic energy potential depends on two parameters: global solar irradiation and photovoltaic panel efficiency. The average solar irradiation in Spain is 1,600 kWh m-2. This paper analyzes the economic feasibility of developing large scale solar photovoltaic power plants in Spain. Equivalent hours between 800-1,800 h year-1 and output power between 100-400 MW have been considered. The profitability analysis has been carried out considering different prices of the electricity produced in the daily market (50-60 € MWh-1). Net Present Value (NPV) and Internal Rate of Return (IRR) were estimated for all scenarios analyzed. A solar PV power plant with 400 MW of power and 1,800 h year-1, reaches a NPV of 196 M€ and the IRR is 11.01%.


2013 ◽  
Vol 17 (2) ◽  
pp. 509-524 ◽  
Author(s):  
Axel Groniewsky

The basic concept in applying numerical optimization methods for power plants optimization problems is to combine a State of the art search algorithm with a powerful, power plant simulation program to optimize the energy conversion system from both economic and thermodynamic viewpoints. Improving the energy conversion system by optimizing the design and operation and studying interactions among plant components requires the investigation of a large number of possible design and operational alternatives. State of the art search algorithms can assist in the development of cost-effective power plant concepts. The aim of this paper is to present how nature-inspired swarm intelligence (especially PSO) can be applied in the field of power plant optimization and how to find solutions for the problems arising and also to apply exergoeconomic optimization technics for thermal power plants.


2013 ◽  
Vol 380-384 ◽  
pp. 3111-3114
Author(s):  
Yi Shi Shu ◽  
Li Li Ma ◽  
Chao Peng

Large scale photovoltaic generation is another way to generate electricity.When a large capacity PV system connected to the grid,much impact could be brought to the grid due to its uncertainty. In this paper, there are research and analysis about the technology and characteristics of the photovoltaic power plants connected to the grid, make a strong practical impacts.


Sign in / Sign up

Export Citation Format

Share Document