Case Histories of Unique Multi-Zone Intelligent Deepwater Sand-Control Completions - How Successes Were Achieved and the Associated Lessons Learned

2008 ◽  
Author(s):  
Stephen J. Jeu ◽  
Wayne Cunningham ◽  
Jacques Braile Salies ◽  
Richard C. Jannise ◽  
Brad Robert Beridon ◽  
...  
2021 ◽  
Author(s):  
Hector Hugo Vizcarra Marin ◽  
Alex Ngan ◽  
Roberto Pineda ◽  
Juan Carlos Gomez ◽  
Jose Antonio Becerra

Abstract Given the increased demands on the production of hydrocarbons and cost-effectiveness for the Operator's development wells, the industry is challenged to continually explore new technology and methodology to improve drilling performance and operational efficiency. In this paper, two recent case histories showcase the technology, drilling engineering, and real-time optimization that resulted in record drilling times. The wells are located on shallow water in the Gulf of Mexico, with numerous drilling challenges, which typically resulted in significant Non-Productive Time (NPT). Through close collaboration with the Operator, early planning with a clear understanding of offset wells challenges, well plan that minimize drilling in the Upper Cretaceous "Brecha" Formation were formulated. The well plan was also designed to reduce the risk of stuck pipe while meeting the requirements to penetrate the geological targets laterally to increase the area of contact in the reservoir section. This project encapsulates the successful application of the latest Push-the-Bit Rotary Steerable System (RSS) with borehole enlargement technology through a proven drilling engineering process to optimize the drilling bottomhole assembly, bit selection, drilling parameters, and real-time monitoring & optimization The records drilling times in the two case histories can be replicated and further improved. A list of lessons learned and recommendations for the future wells are discussed. These include the well trajectory planning, directional drilling BHA optimization, directional control plan, drilling parameters to optimize hole cleaning, and downhole shocks & vibrations management during drilling and underreaming operation to increase the drilling performance ultimately. Also, it includes a proposed drilling blueprint to continually push the limit of incremental drilling performance through the use of RSS with hydraulics drilling reamers through the Jurassic-age formations in shallow waters, Gulf of Mexico.


2021 ◽  
pp. 1-14
Author(s):  
Ashutosh Dikshit ◽  
Amrendra Kumar ◽  
Glenn Woiceshyn

Summary Interest is high in a method to reliably run single-trip completions without involving complex/expensive technologies (Robertson et al. 2019). The reward for such a design would be reduced rig time, safety risks, and completion costs. As described herein, a unique pressure-activated sliding side door (PSSD) valve was developed and field tested to open without intervention after completion is circulated to total depth (TD) and a liner hanger and openhole isolation packers are set. A field-provensliding-sleeve door (SSD) valve that required shifting via a shifting tool run on coiled tubing, slickline (SL), or wireline was upgraded to open automatically after relieving tubing pressure once packers (and/or a liner hanger) are set. This PSSD technology, which is integrable to almost any type of sand control screen, is equipped with a backup contingency should the primary mechanism fail to open. Once opened, the installed PSSDs can be shifted mechanically with unlimited frequency. The two- or three-position valve can be integrated with inflow control devices (ICDs) (includes autonomous ICDs/autonomous inflow control valves) and allows mechanical shifting at any time after installation to close, stimulate or adjust ICD settings. After a computer-aided design stage to achieve all the operational/mechanical requirements, prototypes were built and tested, followed by field installations. The design stage provided some challenges even though the pressure-activation feature was being added to a mature/proven SSD technology. Prototype testing in a full-scale vertical test well proved valuable because it revealed failure modes that could not have appeared in the smaller-scale laboratory test facilities. Lessons learned from the first field trial helped improve onsite handling procedures. The production logging tool run on first installation confirmed the PSSDs with ICDs opened as designed. The second field installation involved a different size and configuration, in which PSSDs with ICDs performed as designed. The unique two- or three-position PSSD accommodates any type of sand control or debris screen and any type of ICD for production/injection. The PSSD allows the flexibility to change ICD size easily at the wellsite. Therefore, this technology can be used in carbonate as well as sandstone wells. Wells that normally could not justify the expense of existing single-trip completion technologies can now benefit from the cost savings of single-trip completions, including ones that require ICD and stimulation options.


2021 ◽  
Author(s):  
Siti Nur Mahirah M Zain ◽  
Nur Hidayah M Zamani ◽  
Sunanda Magna Bela ◽  
Jagaan AL Selladurai ◽  
Saharul Hashim ◽  
...  

Abstract Field D is a massive oil-producing field, which consists of more than 15 blocks that have been developed since 1996. All types of completion methods, from openhole stand-alone screens and cased-hole circulating packs to frac packs, have been applied to help maximize field productivity while keeping sand issues to an acceptable level. However, some wells have begun to encounter sand issues, causing a drop in productivity and in some cases become shut-in because of sand accumulation in the tubing. Small fines (<40 micron) are particularly prominent in the produced sand based on samples collected. A field development revisiting campaign was launched to target new drainage points and recover attic oil using existing slots to sidetrack to the targeted zone and install a new downhole sand control completion. The preferred treatment method is an extension pack (EP) after considering reservoir characteristics, namely close proximity to a coal layer, low permeability, and small fines production, among others. These challenges were addressed by combining the oriented perforation design and optimal sand control completion system using a single-trip multizone system, enhanced single-trip multizone system, and a stack pack with a properly designed proppant pumping strategy using xanthan carrier fluid, a fines-control acid system, and 20/40-mesh ceramic proppant with a 10-gauge wire-wrapped screen. Numerous sand control software simulations were performed to achieve tip screenout (TSO) and a sufficient pack factor while addressing all of the wellbore conditions. For the first time in this field, conductivity enhancer material was applied by dry coating it to proppant on-the-fly with the goal of controlling fines migration through the proppant pack, thus increasing porosity and leading to long-term conductivity. The process design, execution, minifrac analysis, and post-job matching for the frac pack treatment are discussed, which lead to the wells producing sand-free at higher than expected reserves and flow rates. Best practices and lessons learned from this campaign can be further used for new upcoming campaigns.


2021 ◽  
Author(s):  
Nadiah Kamaruddin ◽  
Nurfuzaini A Karim ◽  
M Ariff Naufal Hasmin ◽  
Sunanda Magna Bela ◽  
Latief Riyanto ◽  
...  

Abstract Field A is a mature hydrocarbon-producing field located in eastern Malaysia that began producing in 1968. Comprised of multistacked reservoirs at heights ranging from 4,000 to 8,000 ft, they are predominantly unconsolidated, requiring sand exclusion from the start. Most wells in this field were completed using internal gravel packing (IGP) of the main reservoir, and particularly in shallower reservoirs. With these shallower reservoirs continuously targeted as good potential candidates, identifying a sustainable sand control solution is essential. Conventional sand control methods, namely IGP, are normally a primary choice for completion; however, this method can be costly, which requires justification during challenging economic times. To combat these challenges, a sand consolidation system using resin was selected as a primary completion method, opposed to a conventional IGP system. Chemical sand consolidation treatments provide in situ sand influx control by treating the incompetent formation around the wellbore itself. The initial plan was to perform sand consolidation followed by a screenless fracturing treatment; however, upon drilling the targeted zone and observing its proximity to a water zone, fracturing was stopped. With three of eight zones in this well requiring sand control, a pinpoint solution was delivered in stages by means of a pump through with a packer system [retrievable test treat squeeze (RTTS)] at the highest possible accuracy, thus ensuring treatment placement efficiency. The zones were also distanced from one another, requiring zonal isolation (i.e., mechanical isolation, such as bridge plugs, was not an option) as treatments were deployed. While there was a major challenge in terms of mobilization planning to complete this well during the peak of a movement control order (MCO) in Malaysia, optimal operations lead to a long-term sand control solution. Well unloading and test results upon well completion provided excellent results, highlighting good production rates with zero sand production. The groundwork processes of candidate identification down to the execution of sand consolidation and temporary isolation between zones are discussed. Technology is compared in terms of resin fluid system types. Laboratory testing on the core samples illustrates how the chemical consolidation process physically manifests. This is used to substantiate the field designs, execution plan, initial results, follow-up, lessons learned, and best practices used to maximize the life of a sand-free producer well. This success story illustrates potential opportunity in using sand consolidation as a primary method in the future.


2021 ◽  
Author(s):  
Marco A Aburto Perez ◽  
Anurag S Yadav ◽  
Steven R Farley

Abstract Based on input from key operators in the Middle East region, a new rotary steerable system (RSS) was launched after a compressed development schedule. This paper describes the development and introduction of the larger tool sizes needed for both onshore and offshore hole sections, including hole sizes from 12 in. and up, in the Middle East. It also outlines the deliberate design of the tool for local assembly and repair. Large diameter (9-1/2 and 11 in.) RSS designs used an existing, smaller design for Middle East applications in both offshore and onshore wells as a basis. When designing these new sizes, engineers took note of lessons learned with smaller sizes of the tool and incorporated design elements for local manufacturing, assembly, and repair. The resulting simple, modular construction enables increased levels of local content and provides for significant reductions in transportation, and therefore associated emissions. Of course, although local content and sustainability are highly desirable, performance is essential, and this paper describes case histories demonstrating how well the new tool worked in real-world Middle East applications. In one notable example, the newly introduced 9 1/2-in. diameter RSS was used to drill an offshore section in the Gulf of Arabia. The tool was mobilized after two older generation RSS had become stuck for days. Consisting primarily of argillaceous limestone, the formation had a history of stuck-pipe events. The new RSS was recommended for this application because of a slicker construction, with a fully rotational bias unit, minimal bottom hole assembly (BHA) stabilization, and an optimized junk slot area, which together help to reduce stuck-pipe risks. The tool drilled to the target depth in a single run, thereby achieving all directional requirements. Notably, after reaching the target depth, the assembly was tripped out of the hole without any requirement for backreaming. This seamless exit, in turn, indicated achieving a smooth wellbore. Other case histories demonstrate results with both new sizes of this tool. The paper also discusses in detail the ability to repair locally and engage the local supply chain. Specifically with Middle East applications in mind, a new, simple RSS design in large diameter versions has demonstrated success in offshore and onshore applications across the region. The design has also proven capabilities for manufacturing and repair local to operations, which enables maximizing in-country value, optimizing use of the tools, and energizing local supply chains.


Author(s):  
Warren Brown ◽  
Geoff Evans ◽  
Lorna Carpenter

Over the course of the past 20 years, methods have been developed for assessing the probability and root cause of bolted joint leakage based on sound engineering assessment techniques. Those methods were incorporated, in part, into ASME PCC-1-2010 Appendix O [7] and provide the only published standard method for establishing bolted joint assembly bolt load. As detailed in previous papers, the method can also be used for troubleshooting joint leakage. This paper addresses a series of actual joint leakage cases, outlines the analysis performed to determine root cause of failure and the actions taken to successfully eliminate future incidents of failure (lessons learned).


2002 ◽  
Vol 42 (1) ◽  
pp. 113
Author(s):  
P. Behrenbruch

Uncertainty in petroleum development projects is most often associated with petroleum reserves. It is the limited amount of subsurface data typically available during the time of development planning that creates this situation. Risks are associated not only with reservoir uncertainty but also with wells and production facilities. Risks for offshore projects, as compared to those onshore, are further compounded by very large capital expenditures and less flexibility in catering for subsurface surprises, or remedial action in case of engineering blunders.These concepts are illustrated using case histories of successful and failed projects. Lessons learned from these and other projects are then summarised and processes for uncertainty and risk management are outlined. Risk and uncertainty cover a wide range of issues, and relate to geoscience, reservoir engineering, well technology, facilities engineering, operations, and project planning and evaluation.


Sign in / Sign up

Export Citation Format

Share Document