A new method of biological start-up in Arak activated sludge wastewater treatment plant

2013 ◽  
Vol 8 (2) ◽  
pp. 234-243 ◽  
Author(s):  
Abdolreza Khalili ◽  
Mohammad Reza Mohebi ◽  
Mohammad Mohebi ◽  
Farideh Ashouri

Starting up a wastewater treatment plant (WWTP) is one of the most important stages of operation. A new method was used to start Arak activated sludge WWTP up, which took in advantages of the other methods. Primarily just one of the basins was in the lane and wastewater entered the plant part by part. At first 1/30, second week 1/15, third week 1/6, and fourth week 1/3 of total inflow came to the plant. Observing little progress of biomass gain, some sludge from a similar treatment plant was added to the system, as seed. This procedure continued so the MLSS of the system, attained the 1/3 total design MLSS which was design MLSS of one basin. In the next two weeks, by using developed sludge of the self-system the second and third basins came in the lane and inflow increased to 2/3 and total flow, respectively. Finally after two months of beginning the start-up and one month after adding the seed total desired biomass was developed and the plant started to waste sludge. Because of cold weather start-up period took a longer time than expected. But even before developing biomass environment friendly results were achieved. After attaining design MLSS, BOD5 and COD removal from 40% and 60% increased to 90% and TSS removal from 70% reached to 96%. Less loading, less foam forming, no bacteriologic and chemical problems, better process control, using less seed, saving costs in sludge transport and avoiding relevant problems were the main advantages of this method.

2017 ◽  
Vol 24 (14) ◽  
pp. 13004-13011 ◽  
Author(s):  
Agnieszka Pajdak-Stós ◽  
Wioleta Kocerba-Soroka ◽  
Janusz Fyda ◽  
Mateusz Sobczyk ◽  
Edyta Fiałkowska

2013 ◽  
Vol 8 (1) ◽  
pp. 1-8

Successful start-up of a full-scale wastewater treatment plant (WWTP) is a key issue for the succeeding operation of WWTP on the one hand and the nutritious phosphorus removal is of great concern on the other. After the construction of Mudanjiang WWTP with a flow rate of 100,000 m3 d-1 in Heilongjiang Province of China, a novel way of start-up through feeding wastewater continuously into the system was attempted against the conventional start-up method of inoculating activated sludge in the aeration tank by feeding wastewater intermittently. Activated sludge was cultivated and proliferated in the aeration tanks instead of dosing acclimated sludge from other source. After one-month’s start-up operation, MLSS, SV and SVI increased to 2.5 kg m-3, 30% and nearly 80% respectively, which indicated that quick and simple start-up had been achieved. After successful start-up, an investigation into phosphorus removal was conducted with the emphasis on influencing factors such as ORP and NOx-N concentration etc. When the aeration tank was switched from aerobic to anaerobic mode, phosphorus removal efficiency of 80% could be realized within the whole treatment system. Experimental results revealed that an ORP of -140 mV and NOX-N of 2 mg l-1 were critical for the anaerobic phosphorus release, and DO in the range of 1.7-2.5 mg l-1, BOD5/TP of 20-30 and SVI of 70~80 as well as SRT of 5 days were the optimal phosphorus removal conditions for the aeration tanks.


2013 ◽  
Vol 1 (1) ◽  
pp. 1-13
Author(s):  
Riyadh M. S. Al-Obaidi

The biological unit in the wastewater treatment plants can be considered the most sensitive treatment units. It begins work with dynamic conditions for several weeks until reach the steady state conditions. Therefore, this study was done to observe aeration tank behavior (activated sludge unit) in the wastewater treatment plant of general hospital complex of Mosul city. Sampling made daily for more than 30 days. The biological treatment monitoring parameter was tested. The study shown that there is need to about 45-60 days to complete the start up work to be the operation stable and successful (if it worked without seeding). There was simple growth of microorganisms with modest treatment of organic matter, and then it rose after 3 first weeks of operation. There was contrary relationship between organic content and suspended solids in the aeration tank; an equation of this relation has been presented. The pH has risen in the first days in the effluent wastewater, then return to be less than influent pH with a relative relation with the activity of the microorganisms and surface aeration in the tank. The EC was simply reduced in the Effluent along with the study.


1990 ◽  
Vol 22 (7-8) ◽  
pp. 131-138
Author(s):  
Ahmed Fadel

Many of Egypt's cities have existing treatment plants under operation that have been constructed before 1970. Almost all of these treatment plants now need rehabilitation and upgrading to extend their services for a longer period. One of these plants is the Beni Suef City Wastewater Treatment Plant. The Beni Suef WWTP was constructed in 1956. It has primary treatment followed by secondary treatment employing intermediate rate trickling filters. The BOD, COD, and SS concentration levels are relatively high. They are approximately 800, 1100, and 600 mg/litre, respectively. The Beni Suef city required the determination of the level of work needed for the rehabilitation and upgrading of the existing 200 l/s plant and to extend its capacity to 440 l/s at year 2000 A description of the existing units, their deficiencies and operation problems, and the required rehabilitation are presented and discussed in this paper. Major problems facing the upgrading were the lack of space for expansion and the shortage of funds. It was, therefore, necessary to study several alternative solutions and methods of treatment. The choice of alternatives was from one of the following schemes: a) changing the filter medium, its mode of operation and increasing the number of units, b) changing the trickling filter to high rate and combining it with the activated sludge process, for operation by one of several possible combinations such as: trickling filter-solids contact, roughing filter-activated sludge, and trickling filter-activated sludge process, c) dividing the flow into two parts, the first part to be treated using the existing system and the second part to be treated by activated sludge process, and d) expanding the existing system by increasing the numbers of the different process units. The selection of the alternative was based on technical, operational and economic evaluations. The different alternatives were compared on the basis of system costs, shock load handling, treatment plant operation and predicted effluent quality. The flow schemes for the alternatives are presented. The methodology of selecting the best alternative is discussed. From the study it was concluded that the first alternative is the most reliable from the point of view of costs, handling shock load, and operation.


1992 ◽  
Vol 25 (4-5) ◽  
pp. 203-209 ◽  
Author(s):  
R. Kayser ◽  
G. Stobbe ◽  
M. Werner

At Wolfsburg for a load of 100,000 p.e., the step-feed activated sludge process for nitrogen removal is successfully in operation. Due to the high denitrification potential (BOD:TKN = 5:1) the effluent total nitrogen content can be kept below 10 mg l−1 N; furthermore by some enhanced biological phosphate removal about 80% phosphorus may be removed without any chemicals.


1997 ◽  
Vol 36 (2-3) ◽  
pp. 1-8 ◽  
Author(s):  
P. Grau ◽  
B. P. Da-Rin

An unusually severe case of toxicity accompanied by activated sludge filamentous bulking was observed at the wastewater treatment plant Sao Paulo-Barueri. Treatment efficiency of the plant, operated without major problems for more than five years before, was significantly hindered for almost six months. Occurrence of toxic shocks was confirmed partly directly but mostly indirectly by inhibition of nitrification and biological phenomena related to toxicity. Several measures adopted, including the recycled activated sludge chlorination, are described in the paper.


1998 ◽  
Vol 37 (12) ◽  
pp. 141-148 ◽  
Author(s):  
B. K. Lee ◽  
S. W. Sung ◽  
H. D. Chun ◽  
J. K. Koo

The objective of this study is to develop an automatic control system for dissolved oxygen (DO) and pH of the activated sludge process in a coke wastewater treatment plant. A discrete type autotuned proportional-integral (PI) controller using an auto-regressive exogenous (ARX) model as a process model was developed to maintain the DO concentration in aerators by controlling the speed of surface aerators. Also a nonlinear pH controller using the titration curve was used to control the pH of influent wastewater. This control system was tested in a pilot scale plant. During this pilot plant experiment, there was small deviation of pH and the electric power consumption of surface aerators was reduced up to 70% with respect to the full operation when the DO set point was 2 mg/l. For real plant operation with this system, the discrete PI controller showed good tracking for set point change. The electricity saving was more than 40% of the electricity consumption when considering surface aerators. As a result of maintaining the DO constantly at the set point by the automatic control system, the fluctuation of effluent quality was decreased and overall improvement of the effluent water quality was achieved.


2008 ◽  
Vol 57 (8) ◽  
pp. 1287-1293 ◽  
Author(s):  
A. Jobbágy ◽  
G. M. Tardy ◽  
Gy. Palkó ◽  
A. Benáková ◽  
O. Krhutková ◽  
...  

The purpose of the experiments was to increase the rate of activated sludge denitrification in the combined biological treatment system of the Southpest Wastewater Treatment Plant in order to gain savings in cost and energy and improve process efficiency. Initial profile measurements revealed excess denitrification capacity of the preclarified wastewater. As a consequence, flow of nitrification filter effluent recirculated to the anoxic activated sludge basins was increased from 23,000 m3 d−1 to 42,288 m3 d−1 at an average preclarified influent flow of 64,843 m3 d−1, Both simulation studies and microbiological investigations suggested that activated sludge nitrification, achieved despite the low SRT (2–3 days), was initiated by the backseeding from the nitrification filters and facilitated by the decreased oxygen demand of the influent organics used for denitrification. With the improved activated sludge denitrification, methanol demand could be decreased to about half of the initial value. With the increased efficiency of the activated sludge pre-denitrification, plant effluent COD levels decreased from 40–70 mg l−1 to < 30–45 mg l−1 due to the decreased likelihood of methanol overdosing in the denitrification filter


2012 ◽  
Vol 7 (1) ◽  
Author(s):  
S. S. Fatima ◽  
S. Jamal Khan

In this study, the performance of wastewater treatment plant located at sector I-9 Islamabad, Pakistan, was evaluated. This full scale domestic wastewater treatment plant is based on conventional activated sludge process. The parameters which were monitored regularly included total suspended solids (TSS), mixed liquor suspended solids (MLSS), mixed liquor volatile suspended solids (MLVSS), biological oxygen demand (BOD), and chemical oxygen demand (COD). It was found that the biological degradation efficiency of the plant was below the desired levels in terms of COD and BOD. Also the plant operators were not maintaining consistent sludge retention time (SRT). Abrupt discharge of MLSS through the Surplus Activated sludge (SAS) pump was the main reason for the low MLSS in the aeration tank and consequently low treatment performance. In this study the SRT was optimized based on desired MLSS concentration between 3,000–3,500 mg/L and required performance in terms of BOD, COD and TSS. This study revealed that SRT is a very important operational parameter and its knowledge and correct implementation by the plant operators should be mandatory.


Sign in / Sign up

Export Citation Format

Share Document