Integrated Project Management Approach for Production Well Tie-In in Upstream Projects-Case Study
Abstract Al Dhafra Petroleum Operations Company Limited, (Joint Venture between ADNOC and KADOC, established in late 2013 and assigned with Onshore and Offshore concession areas in Abu Dhabi) had the challenging task to achieve the sustainability of crude production to 40,000 BOPD by end of 2020 from their Haliba field. Current production profile with available wells could not meet that target, for which additional 4 production well Tie-in and construction of 8 km 6″ flow line became necessary within next 3 months. Regular Tie-in program may complete the first Tie-in only by Q2, 2021 and no possibility of enhancing this Tie-in works by 2020. Al Dhafra Management has appointed the Project Management Team (PMT) to take up the challenge by attempting many methods and the timeline was very limited (approximately 90days) to obtain First Oil from those wells.