Challengeable Engineering Design of a Deck for Coiled Tubing Well Abandonment on a Dynamic Positioning Barge

2019 ◽  
Author(s):  
Esmaeil Bahrami ◽  
Mahbod Seyednia ◽  
Ali Akbar Mosallaie Barzoki ◽  
Alireza Zangenehvar ◽  
Seyedebrahim Rabbani
2021 ◽  
Author(s):  
Oleksandr Spuskanyuk ◽  
David C Haeberle ◽  
Brandon Max Baumert ◽  
Brian Matthew King ◽  
Benjamin T Hillier

Abstract The growing number of upcoming well abandonments has become an important driver to seek efficiencies in optimizing abandonment costs while establishing long term well integrity and complying with local regulatory requirements. With an increasing global inventory of Plug and Abandonment (P&A) candidates, Exxonmobil has been driven to look for the most reliable, safe, and cost-efficient P&A technologies. ExxonMobil's P&A guidelines are consistent with and often more stringent than the local regulatory requirements but are also achievable, at least in part, with rigless technologies, leading to a more cost-efficient approach while ensuring well integrity. The objective of this paper is to demonstrate the success of rigless abandonments and their benefits compared to rig-based solutions. When developing a well abandonment plan, it is essential to consider a number of factors. These include local regulations, identification of zones to be isolated and suitable caprocks, and recognition of constraints including well history, conditions and uncertainties. Teams should begin with low cost operations without a rig if possible, estimate costs and effectiveness to achieve the barrier requirements, and evaluate batch operation opportunities for multi-well programs. ExxonMobil case studies are shown to help describe in detail how to make decisions about applicability of rigless abandonment options and how to properly execute such abandonments to achieve compliance with the barrier requirements. It has been demonstrated that significant cost savings can be achieved by staging the abandonment program in a way that lower cost technologies are utilized during the early stages of well abandonment, starting with wireline where possible, followed by coiled tubing and finally by a pulling unit, as appropriate. P&A execution could be achieved without a rig in a majority of cases, including most offshore wells, with the need to use a rig only in special circumstances or phases of execution. It is important to note that the barrier placement and safety of rigless P&A execution will not be compromised, as compared to the rig-based P&As. Additional cost savings could be achieved by further optimizing P&A design at the well design stage, ensuring that there are no built-in limiters that would prevent rigless P&A execution at the end of well life. Several case studies from ExxonMobil's global offshore experience demonstrate the feasibility and effectiveness of rigless P&A operations, with significant cost savings compared to rig-based P&As. It has been evident that rigless P&A choice is applicable to the variety of ExxonMobil's P&A projects of different complexities, with the same or superior quality of abandonment and safety record.


2011 ◽  
Author(s):  
Angel Pando ◽  
Luciano Bravo ◽  
Gustavo Cardona ◽  
Bladimir Lopez ◽  
Otoniel Acevedo

2017 ◽  
Author(s):  
David Giam ◽  
Jorge Santiapichi ◽  
Martijn Bogaerts ◽  
Darby Herrington

2004 ◽  
Author(s):  
S. Kirby ◽  
G. Skelly ◽  
D. Gordon ◽  
S. Sheed

2021 ◽  
Author(s):  
Takeru Okuzawa ◽  
Kushal Gupta ◽  
Tetsuro Takanishi ◽  
Ahmedagha Eldaniz Hamidzada

Abstract In workover phase prior to commencing sidetrack operation, it is required to recover old existing completion string for isolating & abandoning existing reservoir section in accordance with well integrity and global well abandonment standards. Prior to utilization of the coiled tubing cementing approach, the practice was to recover all existing completion by cutting and pulling out the dual tubing or mill the permanent packer. After all the completion recovery, spot and squeeze cementing operations were conducted. However a major drawback of this process is, until recovering some part of completion string, the actual physical condition of the completion strings remains unknown and it poses high risk to get stuck in cased hole or end up in loosing accessibility inside completion string due to corrosion. Furthermore, in some of the old wells had failure to recover completion components like a dual flow assembly and a dual packer due to completion age, had led to improper zonal isolation. Even if all the old existing completion is recovered successfully, it consumes a lot of operation time and several fishing trips with overshot or junk mill BHA (Bottom Hole Assembly). In order to minimize the risk of being stuck or loosing accessibility and ending up failing to recover existing completion and to save operational time, the coiled tubing cementing was conducted to isolate existing reservoir and leave remaining parts of completion downhole. During the operation phase, injectivity test was performed by pumping sea water followed by bull heading kill fluid in to the reservoir. Losses rate was evaluated while observing the well, a high viscosity pill was spotted in order to treat losses and control loss rate. Coiled tubing was rigged up on Long string and run in hole to tag a landing nipple in existing completion string in order to have reference of depth corrected against ORTE (Original Rotary Table Elevation) depths while using the coiled tubing for operations. After having correct reference of depth with tagging completions nipple accessory, coiled tubing with slim OD cementing BHA was run in hole to tag PBTD (Plug Back Total Depth) and then picked up to certain depth while spotting cement slurry at controlled speed. Once the complete amount of slurry was spotted during picking up coiled tubing was pulled out to be away from cement slurry and then coiled tubing BOP (Blow Out Preventer) was closed and cement was squeezed in to the formation. After squeezing pre determined volume or archiving the lock up pressure, coiled tubing was pulled further up and circulated out to ensure all cement slurry out from coiled tubing (inside and outside). Top of cement was confirmed by tagging with the milling assembly connected to coiled tubing and the pressure test was performed after waiting on cement to confirm the integrity of the barrier. For short string, similar abandonment plug process was followed as that of the long string. After performing tagging operations, cement was spotted while pulling out the coil tubing to certain depth and then coil tubing was picked up above the cement to squeeze cement in to the formation. Similar coiled tubing cement operation for isolating lower perforations was performed on three other wells, and proper zonal isolation was achieved against reservoirs. This improved approach of abandoning lower reservoir prior to completions recovery proved to save 2-3 days of rig operational time in comparison to previous operations practices of recovering existing completion completely & then perform cementing operations for zonal isolation against each reservoir. Based on the successful result in three wells, it is concluded that this coiled tubing cement operation is effective for zonal isolation and provide savings in operation days.


2013 ◽  
Author(s):  
Nick Keith Long ◽  
Scott Fraser Ashby ◽  
Song Yan ◽  
Reawat Wattanasuwankorn ◽  
Hj Jameel Basheer Ahmed ◽  
...  

Author(s):  
Michael T. Postek

The term ultimate resolution or resolving power is the very best performance that can be obtained from a scanning electron microscope (SEM) given the optimum instrumental conditions and sample. However, as it relates to SEM users, the conventional definitions of this figure are ambiguous. The numbers quoted for the resolution of an instrument are not only theoretically derived, but are also verified through the direct measurement of images on micrographs. However, the samples commonly used for this purpose are specifically optimized for the measurement of instrument resolution and are most often not typical of the sample used in practical applications.SEM RESOLUTION. Some instruments resolve better than others either due to engineering design or other reasons. There is no definitively accurate definition of how to quantify instrument resolution and its measurement in the SEM.


Sign in / Sign up

Export Citation Format

Share Document