Transient electromagnetic response of the Teutonic Bore orebody

Geophysics ◽  
1986 ◽  
Vol 51 (4) ◽  
pp. 957-963 ◽  
Author(s):  
G. Buselli ◽  
K. G. McCracken ◽  
M. Thorburn

Transient electromagnetic (TEM) measurements have been made with SIROTEM on four separate surveys over the Teutonic Bore orebody (Western Australia), both before mining operations began and subsequently during different stages of stripping overburden from the mineral deposit. In the late stage of the transient decay the target response was relatively free of the overburden and host‐rock response. Beyond ∼ 6 ms, the maximum anomalous response was a factor of 8 to 10 greater than the combined overburden and host‐rock response. Analog modeling with a copper plate in free space shows that the TEM response of the target consists of a single peak at early delay times, while at delay times beyond ∼ 4.2 ms, the response becomes a double‐peak anomaly with a low directly over the top of the plate. Mathematical modeling of the TEM response with a free‐space infinitely thin plate produces profile characteristics similar to those obtained by analog modeling beyond a delay time of ∼ 4.2 ms. Inversion of premining survey profiles in the delay time range 7.0 to 13.2 ms gives values of 82 m for target depth d, and 86 degrees for dip angle θ. These agree well with the values d = 86 m and θ = 82 degrees derived from drilling data. A target conductance value in the range 250 to 320 S is obtained from the TEM data, indicating that the massive sulfide target is highly conductive. Responses calculated for surveys made during overburden stripping are lower than corresponding field values at early delay times because of the absence of overburden response in the model measurements. At delay times beyond 8.5 ms, the model values are consistent with the field values. These results indicate that for a case similar to the Teutonic Bore orebody, where the maximum anomalous late‐time response is a factor of 8 to 10 times greater than the background response, important target parameters may be derived from free‐space models.

Geophysics ◽  
1992 ◽  
Vol 57 (9) ◽  
pp. 1116-1126 ◽  
Author(s):  
James E. Hanneson

An algorithm for computing the transient electromagnetic (TEM) response of a dipping plate in a conductive half‐space has been developed. For a stationary [Formula: see text] current loop source, calculated profiles simulate the response of the University of Toronto electromagnetic system (UTEM) over a plate in a 1000 Ω ⋅ m half‐space. The objective is to add to knowledge of the galvanic process (causing poloidal plate currents) and the local induction process (causing toroidal currents) by studying host and plate currents with respect to surface profiles. Both processes can occur during TEM surveys. Plates are all [Formula: see text] thick with various depths, dips, and conductances. Calculated host and plate currents provide quantitative examples of several effects. For sufficiently conductive plates, the late time currents are toroidal as for a free‐space host. At earlier times, or at all times for poorly conducting plates, the plate currents are poloidal, and the transitions to toroidal currents, if they occur, are gradual. At very late times, poloidal currents again dominate any toroidal currents but this effect is rarely observed. Stripped, point‐normalized profiles, which reflect secondary fields caused by the anomalous plate currents, illustrate effects such as early time blanking (caused by noninstantaneous diffusion of fields into the target), mid‐time anomaly enhancement (caused by galvanic currents), and late time plate‐in‐free‐space asymptotic behavior.


Geophysics ◽  
1986 ◽  
Vol 51 (6) ◽  
pp. 1291-1297 ◽  
Author(s):  
Yang Sheng

Early‐time and late‐time apparent resistivity approximations have been widely used for interpretation of long‐offset transient electromagnetic (LOTEM) measurements because it is difficult to find a single apparent resistivity over the whole time range. From a physical point of view, Dr. C. H. Stoyer defined an apparent resistivity for the whole time range. However, there are two problems which hinder its use: one is that there is no explicit formula to calculate the apparent resistivity, and the other is that the apparent resistivity has no single solution. A careful study of the two problems shows that a numerical method can be used to calculate a single apparent resistivity. A formula for the maximum receiver voltage over a uniform earth, when compared with the receiver voltage for a layered earth, leads to the conclusion that, in some cases, a layered earth can produce a larger voltage than any uniform earth can produce. Therefore, our apparent resistivity definition cannot be applied to those cases. In some other cases, the two possible solutions from our definition do not merge, so that neither of them is meaningful for the whole time range.


Geophysics ◽  
1981 ◽  
Vol 46 (1) ◽  
pp. 53-64 ◽  
Author(s):  
A. P. Raiche ◽  
B. R. Spies

A set of apparent conductivity master curves has been calculated for the coincident loop transient electromagnetic (TEM) method used over a two‐layer earth. Conductivity contrasts range from 0.001 to 1000. Loop radius/layer depth ratios range from 0.01 to 100. The time range is sufficient to see the entire shape of the curves from the early to the late time asymptotes. These curves allow the determination of the parameters of a two‐layer earth for accurate data over a sufficient time range. Examples using the curves to interpret multilayered earths are given. The curves are also used to show the limitations placed on interpretation by existing TEM equipment.


Geophysics ◽  
2012 ◽  
Vol 77 (1) ◽  
pp. E91-E99 ◽  
Author(s):  
Ralf Schaa ◽  
Peter K. Fullagar

We derived analytic expressions for the time integrals of vertical and horizontal transient B-field responses on a conductive half-space excited by a rectangular-loop source. These formulas were applied in two ways in a fast transient electromagnetic (TEM) inversion scheme. Indefinite integrals were used to extrapolate measured TEM decays to early and late time to convert the observed data to resistive limits. Definite integrals over all time provided estimates for the resistive limit response of host-rock. An apparent conductivity of the host was calculated from the resistive limits via a simple least-squares formulation. These applications of the formulas were tested on synthetic and real TEM data.


Geophysics ◽  
1985 ◽  
Vol 50 (6) ◽  
pp. 1002-1019 ◽  
Author(s):  
Peggie R. Gallagher ◽  
Stanley H. Ward ◽  
G. W. Hohmann

The computer program PLATE, developed at the University of Toronto, models the electromagnetic (EM) response of an inductively thin plate in free space. We used PLATE to compute two components of the time derivative of the magnetic field for a range of models for the EM37 fixed‐source transient system ([Formula: see text] loop). Analysis of the response curves produced methods of interpretation for obtaining plate geometry and conductance. The overall width of an anomaly, the distance between peaks and the width of the updip lobes, can provide an estimate of depth. Dip has the dominant effect on the ratio of the peak amplitudes. A rough estimate of plate size and the position in time (early or late) of the currents is essential before proceeding with interpretation. Strike length is not obviously reflected in the shape of the curves, but depth extent is indicated by the rate at which the downdip tail returns to the baseline, except for vertical plates. For vertical plates, curve matching may be the only method of obtaining an estimate of depth extent. Varying conductance for a particular model in free space affects whether a channel represents an early, intermediate, or late time response. The shape of a profile varies with the time of measurement. The estimated time constant can be used to calculate the conductance, provided an estimate of the shortest dimension of the plate is available. Extinction angles appear frequently for plates of small depth extent but do not occur for plates which are of infinite strike and depth extent with respect to the size of the transmitting loop.


Geophysics ◽  
1986 ◽  
Vol 51 (7) ◽  
pp. 1462-1471 ◽  
Author(s):  
Brian R. Spies ◽  
Dwight E. Eggers

Problems and misunderstandings arise with the concept of apparent resistivity when the analogy between an apparent resistivity computed from geophysical observations and the true resistivity structure of the subsurface is drawn too tightly. Several definitions of apparent resistivity are available for use in electromagnetic methods; however, those most commonly used do not always exhibit the best behavior. Many of the features of the apparent resistivity curve which have been interpreted as physically significant with one definition disappear when alternative definitions are used. It is misleading to compare the detection or resolution capabilities of different field systems or configurations solely on the basis of the apparent resistivity curve. For the in‐loop transient electromagnetic (TEM) method, apparent resistivity computed from the magnetic field response displays much better behavior than that computed from the induced voltage response. A comparison of “exact” and “asymptotic” formulas for the TEM method reveals that automated schemes for distinguishing early‐time and late‐time branches are at best tenuous, and those schemes are doomed to failure for a certain class of resistivity structures (e.g., the loop size is large compared to the layer thickness). For the magnetotelluric (MT) method, apparent resistivity curves defined from the real part of the impedance exhibit much better behavior than curves based on the conventional definition that uses the magnitude of the impedance. Results of using this new definition have characteristics similar to apparent resistivity obtained from time‐domain processing.


Author(s):  
Matt Boring ◽  
Mike Bongiovi ◽  
David Warman ◽  
Harold Kleeman

Welds that are made onto an operating pipeline cool at an accelerated rate as a result of the flowing pipeline contents cooling the weld region. The accelerated cooling rates increase the probability of forming a crack-susceptible microstructure in the heat-affected zone (HAZ) of in-service welds. The increased risk of forming such microstructures makes in-service welds more susceptible to hydrogen cracking compared to welds that do not experience accelerated cooling. It is understood within the pipeline industry that hydrogen cracking is a time-dependent failure mechanism. Due to the time-dependent nature and susceptibility of in-service welds to hydrogen cracking, it is common to delay the final inspection of in-service welds. The intent of the delayed inspection is to allow hydrogen cracks, if they were going to occur, to form so that the inspection method could detect them and the cracks could repaired. Many industry codes provide a single inspection delay time. By providing a single inspection delay time it is implied that the inspection delay time should be applied for all situations independent of the welding conditions or any other preventative measures the company may employee. There are many aspects that should be addressed when determining what should be considered an appropriate inspection delay time and these aspects can vary the inspection delay time considerably. Such factors include the cooling characteristics of the operating pipeline, the welding procedure that is being followed, the chemical composition of the material being welded and if any preventative measures such as post-weld heating are applied. The objective of this work was to provide an engineering justification for realistic minimum inspection delay times for different in-service welding scenarios. The minimum inspection delay time that was determined was based on modelling results from a previously developed two-dimensional hydrogen diffusion model that predicts the time to peak hydrogen concentration at any location within a weld HAZ. The time to peak hydrogen concentration was considered equal to the minimum inspection delay time since the model uses the assumption that if a weld was to crack the cracking would occur prior to or at the time of peak hydrogen concentration. Several factors were varied during the computer model runs to determine the effect they had on the time to peak hydrogen concentration. These factors included different welding procedures, different material thicknesses and different post-weld heating temperatures. The post-weld heating temperatures were varied between 40 F (4 C) and 300 F (149 C). The results of the analysis did provide justification for reducing the inspection delay time to 30 minutes or less depending on the post-weld heating temperature and pipeline wall thickness. This reduction in inspection delay time has the potential to significantly increase productivity and reduce associated costs without increasing the associated risk to pipeline integrity or public safety.


2017 ◽  
Vol 9 (1) ◽  
pp. 16-22 ◽  
Author(s):  
Vladimir S Khorev ◽  
Anatoly S Karavaev ◽  
Elena E Lapsheva ◽  
Tatyana A Galushko ◽  
Mikhail D Prokhorov ◽  
...  

Objective: We assessed the delay times in the interaction between the autonomic regulatory loop of Heart Rate Variability (HRV) and autonomic regulatory loop of photoplethysmographic waveform variability (PPGV), showing low-frequency oscillations. Material and Methods: In eight healthy subjects aged 25–30 years (3 male, 5 female), we studied at rest (in a supine position) the simultaneously recorded two-hour signals of RR intervals (RRIs) chain and finger photoplethysmogram (PPG). To extract the low-frequency components of RRIs and PPG signal, associated with the low-frequency oscillations in HRV and PPGV with a frequency of about 0.1 Hz, we filtered RRIs and PPG with a bandpass 0.05-0.15 Hz filter. We used a method for the detection of coupling between oscillatory systems, based on the construction of predictive models of instantaneous phase dynamics, for the estimation of delay times in the interaction between the studied regulatory loops. Results: Averaged value of delay time in coupling from the regulatory loop of HRV to the loop of PPGV was 0.9±0.4 seconds (mean ± standard error of the means) and averaged value of delay time in coupling from PPGV to HRV was 4.1±1.1 seconds. Conclusion: Analysis of two-hour experimental time series of healthy subjects revealed the presence of delay times in the interaction between regulatory loops of HRV and PPGV. Estimated delay time in coupling regulatory loops from HRV to PPGV was about one second or even less, while the delay time in coupling from PPGV to HRV was about several seconds. The difference in delay times is explained by the fact that PPGV to HRV response is mediated through the autonomic nervous system (baroreflex), while the HRV to PPGV response is mediated mechanically via cardiac output.


2020 ◽  
Vol 224 (1) ◽  
pp. 669-681
Author(s):  
Sihong Wu ◽  
Qinghua Huang ◽  
Li Zhao

SUMMARY Late-time transient electromagnetic (TEM) data contain deep subsurface information and are important for resolving deeper electrical structures. However, due to their relatively small signal amplitudes, TEM responses later in time are often dominated by ambient noises. Therefore, noise removal is critical to the application of TEM data in imaging electrical structures at depth. De-noising techniques for TEM data have been developed rapidly in recent years. Although strong efforts have been made to improving the quality of the TEM responses, it is still a challenge to effectively extract the signals due to unpredictable and irregular noises. In this study, we develop a new type of neural network architecture by combining the long short-term memory (LSTM) network with the autoencoder structure to suppress noise in TEM signals. The resulting LSTM-autoencoders yield excellent performance on synthetic data sets including horizontal components of the electric field and vertical component of the magnetic field generated by different sources such as dipole, loop and grounded line sources. The relative errors between the de-noised data sets and the corresponding noise-free transients are below 1% for most of the sampling points. Notable improvement in the resistivity structure inversion result is achieved using the TEM data de-noised by the LSTM-autoencoder in comparison with several widely-used neural networks, especially for later-arriving signals that are important for constraining deeper structures. We demonstrate the effectiveness and general applicability of the LSTM-autoencoder by de-noising experiments using synthetic 1-D and 3-D TEM signals as well as field data sets. The field data from a fixed loop survey using multiple receivers are greatly improved after de-noising by the LSTM-autoencoder, resulting in more consistent inversion models with significantly increased exploration depth. The LSTM-autoencoder is capable of enhancing the quality of the TEM signals at later times, which enables us to better resolve deeper electrical structures.


2020 ◽  
Vol 12 (15) ◽  
pp. 5940
Author(s):  
Dani Broitman

Planning delay time is a ubiquitous but under-researched land use regulation method. The aim of this study is to link planning delay time with the loss of urban locally provided ecosystem services (ULPES) caused by land development. Our main hypothesis is that the planning delay is an informal tool that ensures social welfare in a given urban area increases even if land is developed and the ULPES associated with the undeveloped land are lost. Whereas the developer’s objective is to maximize his profits, the planner’s target is to achieve the greatest social welfare, as calculated by considering public interest based on the value of open space and the developer’s expected profits. Our results show that, when the ULPES provided by an undeveloped parcel are sufficiently high, planning delay times can be used to prevent the execution of low quality initiatives and to only permit projects that improve general welfare and justify the potential ULPES loss. Planning delay times are interpreted as the expression of continuous negotiation between the interests of the public and those of real-estate developers, regarding the value of ULPES. The implication of the study is that ULPES values are introduced using a simple game-theoretic model allowing interaction between developers and planning authorities. The main significance is an alternative explanation for planning delay times as a consequence of ongoing negotiations between developers and urban planners that represent the general public in the city.


Sign in / Sign up

Export Citation Format

Share Document