Dynamic scheduling of concurrent tasks with cost performance trade-off

Author(s):  
Peng Yang ◽  
Dirk Desmet ◽  
Francky Catthoor ◽  
Diederik Verkest
2019 ◽  
Vol 11 (5) ◽  
pp. 1256 ◽  
Author(s):  
Myung-Hun Kim ◽  
Eul-Bum Lee ◽  
Han-Suk Choi

The main subject of this research is to develop a forecast and mitigation model of schedule and cost performance during a detailed engineering stage of offshore engineering, procurement and construction (EPC) projects. The weight factors of major elements in detailed engineering completion rating index system (DECRIS) were measured using a fuzzy inference system (FIS) and an analytic hierarchy process (AHP). At five key engineering milestones, from an EPC contract being awarded to the start of construction, detailed engineering maturities were assessed in fourteen historical offshore EPC projects using the DECRIS model. DECRIS cutoff scores for successful project execution were defined at the key engineering milestones. A schedule and cost performance was forecasted and validated through comparison of DECRIS and other models using statistical confidence of a fuzzy set qualitative comparative analysis (fsQCA) and a regression analysis. As a mitigation method for engineering risks to EPC contractors, engineering resource enhancement is recommended for trade-off optimization of cost overrun using a Monte Carlo simulation. The main contribution of this research is that EPC contractors could continuously forecast construction costs and schedule performance utilizing the DECRIS model, and could review the adequacy of engineering resources, assessing the trade-off between said resources and cost/schedule risk mitigation.


2019 ◽  
Vol 6 (2) ◽  
pp. 26-37
Author(s):  
Liem Stefani Meilia Gunawan

Nowadays, the minimization of project time and cost is an important issue. However, time and cost problems are difficult to solve. They are affected by the uncertain factor. Then, the construction project always fails to achieve the effectiveness of time and cost performance. It causes delays and cost overrun. In this research, SOS-NN-LSTM is required to establish the estimate schedule to completion (ESTC) and estimate cost to completion (ECTC) prediction model based on time now performance. Then, the prediction model will be integrated with MOSOS to obtain the optimal prediction value. The integration is needed because there is no direct equation to calculate the ESTC and ECTC. The Pareto curve identified based on the prediction values of MOSOS. The Pareto curve is used to determine the optimal trade-off between project duration and project cost. Then, the indifference curve is used to solve the trade-off problem between estimate schedule at completion (ESAC) dan estimate cost at completion (ECAC) which give the decision-maker preference.


1982 ◽  
Vol 14 (2) ◽  
pp. 109-113 ◽  
Author(s):  
Suleyman Tufekci
Keyword(s):  

2012 ◽  
Vol 11 (3) ◽  
pp. 118-126 ◽  
Author(s):  
Olive Emil Wetter ◽  
Jürgen Wegge ◽  
Klaus Jonas ◽  
Klaus-Helmut Schmidt

In most work contexts, several performance goals coexist, and conflicts between them and trade-offs can occur. Our paper is the first to contrast a dual goal for speed and accuracy with a single goal for speed on the same task. The Sternberg paradigm (Experiment 1, n = 57) and the d2 test (Experiment 2, n = 19) were used as performance tasks. Speed measures and errors revealed in both experiments that dual as well as single goals increase performance by enhancing memory scanning. However, the single speed goal triggered a speed-accuracy trade-off, favoring speed over accuracy, whereas this was not the case with the dual goal. In difficult trials, dual goals slowed down scanning processes again so that errors could be prevented. This new finding is particularly relevant for security domains, where both aspects have to be managed simultaneously.


Sign in / Sign up

Export Citation Format

Share Document