A Life Extension Perspective for a CANDU-6 NPP: Gentilly-2 Plant Condition Assessments

Author(s):  
Marc Aubray

To extend the life of a CANDU-6 reactor beyond its original design life requires a major investment for the replacement of reactor components (380 pressure and calandria tubes). After a preliminary technical and economical feasibility study [ref 1], Hydro-Quebec, owner of the Gentilly-2 NPP, has decided to perform a more detailed assessment to: • Get assurance that it is technically and economically viable to extend Gentilly-2 for another 20 years beyond the original design life; • Identify the detailed work to be done; • Define the overall cost and the general schedule; • Ensure an adequate licensing strategy to restart after refurbishment; • Complete all the Environmental Impact Studies required to obtain the government authorizations. Two processes have been used to assess the “health” of the station Systems, Structures and Components (SSCs): • The Plant Life Management Studies (PLIM) for approximately 10 critical SSC or families of SSC (PLIM Studies); • The Condition Assessment Studies for other SSC with a lower impact on the Plant production or safety. These two processes are briefly presented in the paper, as they were realized and applied at Gentilly-2 NPP.

Author(s):  
John V. Sharp ◽  
Edmund G. Terry ◽  
John Wintle

Many offshore installations in the North Sea have now exceeded their original design life and are in a life extension phase. A Framework of six processes has been developed for the management of ageing of Safety Critical Elements (SCEs) in offshore installations. The processes include an analysis of the effect of ageing modes on SCE performance. Examples of performance indicators for typical SCEs are proposed based on how their condition and performance as may be affected by physical deterioration and other effects of ageing. Indicators for calibrating the maturity and effectiveness of the management processes are also suggested.


2010 ◽  
Vol 132 (5) ◽  
Author(s):  
David H. Creates

Fatigue evaluation in B31.1 is currently done based on equations 1 and 2 of ASME B31.1-2007 Power Piping, which only considers the displacement load ranges. However, fatigue damage, in addition to displacement load ranges, is occurring in B31.1 piping due to pressure cycling and thermal gradients. To exacerbate this, power plant design pressures and temperatures are rising, new materials are being introduced, pipes and attached components are becoming increasingly thick, and owners are requiring power plants to heat-up and cool-down at faster rates. Also, power plant owners are more and more interested in extending the life of power plants beyond their original design life. This article takes the first step in addressing the pressing need to address this additional fatigue damage by quantifying thermal gradients in the prevalent B31.1 welding end transitions in Fig. 127.4.2, or tapered transition joints (TTJs) in Appendix D, of ASME B31.1-2007 Power Piping by formulae to be able to evaluate their contribution to fatigue (see PVP2009-77148 [A Procedure to Evaluate a B31.1 Welding End Transition Joint to Include the Fatigue Effects of Thermal Gradients for Design and Plant Life Extension]). The disadvantage of this approach is that the conservatisms inherent in the calculations of thermal gradients, as per ASME Section III Subsection NB3600-2007, are also inherent in these calculations and may produce unacceptable results when evaluated as per PVP2009-77148 [A Procedure to Evaluate a B31.1 Welding End Transition Joint to Include the Fatigue Effects of Thermal Gradients for Design and Plant Life Extension]. If the results are unacceptable, it is a warning that something else needs to be done. The advantage of this approach is that it eliminates the need for a computer program to quantify these thermal gradients, a computer program that is not normally accessible to the B31.1 designer anyway. Instead, the formulae use the data that are available to the B31.1 designer, namely, physical geometry, thermal conductivity, and rate of temperature change in the fluid in the pipe. This will further help to preserve the integrity of the piping pressure boundary and, consequently, the safety of personnel in today’s power plants and into the future.


Author(s):  
Abe Nezamian ◽  
Joshua Altmann

The ageing of offshore infrastructure presents a constant and growing challenge for operators. Ageing is characterised by deterioration, change in operational conditions or accidental damages which, in the severe operational environment offshore, can be significant with serious consequences for installation integrity if not managed adequately and efficiently. An oil field consisting of twelve well head platforms, a living quarter platform (XQ), a flare platform (XFP) and a processing platform (XPA) are the focus of this paper, providing an overview of the integrity assessment process. In order to ensure technical and operational integrity of these ageing facilities, the fitness for service of these offshore structures needs to be maintained. Assessments of the structural integrity of thirteen identified platforms under existing conditions were undertaken as these platforms are either nearing the end of their design life or have exceeded more than 50% of their design life. Information on history, characteristic data, condition data and inspection results were collected to assess the current state and to predict the future state of the facility for possible life extension. The information included but was not limited to as built data, brown fields modifications, additional risers and clamp-on conductors and incorporation of subsea and topside inspection findings. In-service integrity assessments, pushover analyses, corrosion control and cathodic protection assessments and weight control reports were completed to evaluate the integrity of these facilities for requalification to 2019 and life extension to 2030. The analytical models and calculations were updated based on the most recent inspection results and weight control reports. A requalification and life extension report was prepared for each platform to outline the performance criteria acceptance to achieve requalification until 2019 and life extension until 2030. This paper documents the methodology to assess the platform structural integrity in order to evaluate platform integrity for the remaining and extended design life. An overview of various aspects of ageing related to these offshore facilities, representing risk to the integrity, the required procedures and re assessment criteria for deciding on life extension of these facilities is presented. This paper also provides an overall view of the structural requirements, justifications and calibrations of the original design for the life extension to maintain the safety level by means of maintenance and inspection programs balancing the ageing mechanisms and improving the reliability of assessment results.


Author(s):  
Jorgen Thomas Wold Eide ◽  
Jan Muren

This paper presents a methodology for performing a lifetime assessment of flexible pipes applicable to re-qualification during the original design life and at life extension. A systematic approach is developed, providing flexible riser and flowline engineers a standardized methodology for determining the current integrity- and risk level. The objective is to provide methodology that is easy to implement, thus enabling consistent assessments of all flexible pipes in the operator’s portfolio. The methods described are taken from work performed in a recent JIP run jointly by MARINTEK/NTNU and 4Subsea, and is based on substantial experiences with lifetime assessment combined with a review of relevant guidelines and standards. Key areas are suggested for industry improvement and recommendations to further developments, to increase both efficiency and quality of the lifetime assessment process.


Author(s):  
Basim Mekha ◽  
Robin Gordon

Abstract As many offshore production systems approach the end of their original Design Life, Operators are faced with the choice of either decommissioning or demonstrating that the original Design Life can be extended (Life Extension). Life extension requires the Operator to perform detailed engineering analyses to verify that the system can be operated safely over the period of Life Extension. In many cases this requires detailed fatigue analysis and inspection programs to demonstrate that original fabrication flaws or fatigue cracks that may have existed during the welding of the riser joints or initiated over the original Design Life will not grow to a critical size resulting in failure. Engineering Critical Assessment (ECA) is now routinely applied in the design and fabrication of new offshore riser systems to develop girth weld flaw acceptance criteria. The resulting flaw acceptance criteria ensure that fabrication flaws will not extend to a critical size over the Design Life and thus the riser still meet its calculated fatigue life. Although ECA procedures for new construction are well established and standard practices have been adopted throughout the industry, ECA procedures for Life Extension have not yet evolved to the same level of acceptance. This paper will review specific issues associated with applying ECA to support Life Extension of offshore Riser Systems. The paper will provide the overall ECA philosophy and methodology for life extension to be adopted for the historical (hindcast or Phase 1) and future (forecast or Phase 2) analysis of the risers. Some thoughts will also be given to the approach implemented to take advantage of the actual weld fabrication data with the focus on the fatigue critical sections of the risers. Finally, the paper will address the requirements for riser in-situ inspection and how the results could be analyzed and applied to the life extension analysis in conjunction with the ECA analysis.


Author(s):  
A. Stacey ◽  
M. Birkinshaw ◽  
J. V. Sharp

With many offshore installations in the UK sector of the North Sea now reaching or being in excess of their original anticipated design life, there is a particular need to evaluate approaches to structural integrity management by offshore operators. Ageing processes can affect the structural integrity of the installation and demonstration of adequate performance beyond its original design life is thus a necessary requirement. This paper addresses the issues relevant to the life extension of ageing installations.


Author(s):  
Solfrid Ha˚brekke ◽  
Lars Bodsberg ◽  
Per Hokstad ◽  
Gerhard Ersdal

A large number of facilities and parts of the infrastructure on the Norwegian Continental Shelf are approaching or have exceeded their original design life. Many fields, however, have remaining recoverable oil and gas reserves which may be profitable if the field’s life is extended. From a safety point of view, the condition of systems, structures and components may not be acceptable for extended operation. Ageing and life extension have been a top priority for the Petroleum Safety Authority Norway (PSA) and PSA has asked SINTEF to conduct a study of various aspects of ageing and life extension. The paper presents main results from the study, including how to document the safety of an ageing facility and how to uphold the safety level by means of a maintenance programme balancing three aspects of ageing: 1) Material degradation, 2) Obsolescence, i.e. operations and technology being “out of date” and 3) Organisational issues. The paper presents six main steps of the life extension process and discusses important issues to consider for operators in a life extension process.


Author(s):  
Jens P. Tronskar

Cost efficient offshore field development often involves tiebacks to existing field infrastructure. Efficient field development requires life extension of existing production facilities and pipelines to accommodate the new field resources over their life expectation. For fields near the tail end of their production the pipelines may be close to the end of their design life, and it must be shown that they have potential for extended life beyond the original design life until the end of the period of operation of the new field. Offshore pipelines are designed and constructed to recognized standards, such as the widely applied DNV OS-F101 2013 Submarine Pipelines Systems and earlier versions. The latest edition of the code was recently issued as a standard with some major updates and a modified code number i.e. DNVGL ST-F101 [1]. As pipelines age, they will inevitably be exposed to various types of degradation and an Operator must be able to both assess the significance of this damage and the pipeline remaining life to ensure that the pipelines do not fail as they age before the end of their design lives. Currently, many pipelines are operated far beyond the original design life and as mentioned above for cost efficient field development the pipeline operator often needs to demonstrate that the pipeline’s useful life can be extended another 10 or in some cases up to 30 years. For some pipelines, new operating conditions will be introduced by tie-in of new fields and this will impact the future rate of degradation. Hence, it cannot be assumed that the future degradation will be similar or less severe than experienced since commissioning of the pipeline. Extension of the life of the pipeline can be demonstrated by adopting methods of analysis that show the line is safe for an extended life under the future expected operating condition. This paper describes the risk based approach applied for pipeline remaining life and life extension analyses based on DNV GL codes and other relevant recommended practices. For illustration of the methodology a typical case of remaining life assessment of and life extension of a gas export pipeline is presented in the Case Study.


Author(s):  
J. Rosen ◽  
D. Johnstone ◽  
P. Sincock ◽  
A. E. Potts ◽  
D. Hourigan

Life extension and asset integrity of Floating Production Unit (FPU) moorings are issues of increasing importance for operators due to changing production requirements, the requirement to extend service life, and circumstances where the met-ocean Basis of Design (BOD) has increased significantly over the life of the field. Reliability methods are gaining increasing acceptance as increased computing power allows large numbers of simulations to be undertaken using realistic fully coupled models that are validated against prior experiments. When applied to the re-qualification and life extension of FPU moorings, particularly with regard to re-qualification and life extension of in-place moorings, reliability analysis offers considerable advantages over conventional deterministic return period design. This paper details the application of a reliability approach to re-qualification and life extension of a turret-moored FPU that had design met-ocean conditions increased significantly over the life of the field. It explores key elements of reliability analysis including the probabilistic characterisation of met-ocean conditions, adequate representation of vessel dynamics and mooring loads in a Response Surface Model, and a selection of algorithms to solve for the system probability of failure. Discussion points include the advantages of the explicit identification of the most likely failure scenario versus uncertainty as to whether the worst design case has been identified, and the potential for rapid reassessment of reliability for specific design conditions (such as a degraded mooring system or a system for which degradation is ongoing). The results of this study demonstrate the significant advantages to the industry conferred by adopting reliability methods in the re-certification and life extension of existing FPU moorings. In particular, the study highlights that conventional mooring code deterministic design methods, whilst adequate for original design purposes, lack sufficient fidelity to address the multi-faceted issue of re-assessment of notionally marginal legacy systems. For a degraded existing mooring, an application of these methods can demonstrate that the level of reliability of the system is still acceptable, whereas a conventional approach may produce an over-conservative indication that the mooring is non-compliant. Applicable to a wide range of FPUs requiring re-qualification or life extension, the techniques discussed also provide pointers to more efficient and reliable mooring design for not just existing, but also for new FPUs.


Sign in / Sign up

Export Citation Format

Share Document