Cofferdam and Hyperbaric “Live” Repair of Gas Pipeline Leaks

Author(s):  
Jens P. Tronskar ◽  
Chon Gee Lee

Offshore pipelines may face many threats. Apart from internal and external corrosion third party threats represent major hazards to submarine pipelines. Recent pipeline leaks caused by third party as well as construction and installation have been repaired online in a two-step process involving installation of a leak clamp followed by a permanent repair by installation of a welded stand-off sleeve. The welding has depending on the water depth been executed in a hyperbaric habitat or in shallow water using purpose built cofferdams. A concept proposed by DNV GL has been successfully applied to repair of leaking submarine pipelines. To ensure the safety of the repair crew the concepts involves using a gas containment barrier installed over a traditional mechanical leak clamp. The gas containment barrier is either purged with inert gas or nitrogen or it is maintained with a constant inert gas pressure that is monitored continuously during the repair. In the event of a sudden gas leak into the gas containment barrier a pre-set pressure relief valve will open and dump the gas leak outside the habitat. This paper describes the details of a few cases of leaking submarine gas pipelines and the immediate causes of the leak, the repair method selection, the repair method details, cofferdam or hyperbaric welding qualification and execution. The paper also describes the various steps in the process to ensure that the pipeline damage is stable and that the repairs can be safely undertaken to restore the pipelines to their original design condition without reduction of pressure or flow rate. The paper describes the method of global and local finite element analyses as well as fracture mechanics assessment by FEA to assess the stability of the flaws causing the gas leaks. The pipelines in question have all been gas transmission lines carrying gas to gas fired power plants for which gas pressure reduction or shutdown were completely unacceptable. Future development is expected to involve development of remotely controlled repairs using similar concepts at water depths where diver/welders cannot be employed due to the various country regulations or simply because the water depths are too deep for saturation divers. Methodology according to DNV RP-A203 [1] is described for qualification of new technology for underwater pipeline repairs. Further references are made to the recent updates to the DNV RP-F113 Pipeline Subsea Repair [2] with regards to requirements for “live” pipeline repairs. The DNV RP-F113 refers to the PRCI Weld Thermal analyses [3] and requirements to perform full scale mock-up tests of the repair as part of the repair method qualification based on DNV OS-F101 Submarine Pipelines [4].

2021 ◽  
Author(s):  
Qiongxiao Wu ◽  
Jianjun Wang ◽  
Jingming Chen ◽  
Pengzheng Li

Abstract Based on the one-dimensional simulation model of lubricating oil system is established and analyzed by using FLOWMASTER software, this paper proposes a new method of optimizing lubricating oil system by PID technology. Ensure that the configuration requirements and control strategies of the relevant accessories of the simulation model are satisfied with the design requirements. Firstly, by simulating lubricating oil pressure fluctuation and lubricating oil flow distribution under Open/Close Valve in different opening and closing time, the optimal opening/closing time of Open/Close Valve is determined to be 0.2 s and 0.5 s respectively. Secondly, by writing the controller script file combined with a controller to realize automatic unloading relief valve simulation, determine the relief valve pressure regulating range of 0∼0.38 MPa, For precision of constant pressure valve of oil spill, the simulation results show that the average 10 m3/h flow caused by pressure changes of about 0.06 MPa. Under the flow sudden change signal of about 40 m3/h, the maximum pressure change is less than 0.1 MPa. Through the simulation results, it is found that most of the lubrication parts in the original design have the phenomenon of flow redundancy, which causes unnecessary pump power loss. The system is optimized by PID technology. By comparing the simulation results before and after optimization, it is found that the speed of constant displacement pump could be changed in time by PID controller, and the flow redundancy could be improved significantly, so the lubricating oil system could be lower consumption and achieve the purpose of optimization.


2018 ◽  
Vol 2018 ◽  
pp. 1-12
Author(s):  
Taeseok Kim ◽  
Wonjun Choi ◽  
Joongoo Jeon ◽  
Nam Kyung Kim ◽  
Hoichul Jung ◽  
...  

During a hypothesized severe accident, a containment building is designed to act as a final barrier to prevent release of fission products to the environment in nuclear power plants. However, in a bypass scenario of steam generator tube rupture (SGTR), radioactive nuclides can be released to environment even if the containment is not ruptured. Thus, thorough mitigation strategies are needed to prevent such unfiltered release of the radioactive nuclides during SGTR accidents. To mitigate the consequence of the SGTR accident, this study was conducted to devise a conceptual approach of installing In-Containment Relief Valve (ICRV) from steam generator (SG) to the free space in the containment building and it was simulated by MELCOR code for numerical analysis. Simulation results show that the radioactive nuclides were not released to the environment in the ICRV case. However, the containment pressure increased more than the base case, which is a disadvantage of the ICRV. To minimize the negative effects of the ICRV, the ICRV linked to Reactor Drain Tank (RDT) and cavity flooding was performed. Because the overpressurization of containment is due to heat of ex-vessel corium, only cavity flooding was effective for depressurization. The conceptual design of the ICRV is effective in mitigating the SGTR accident.


2019 ◽  
Vol 109 ◽  
pp. 00119
Author(s):  
Volodymyr Yemelianenko ◽  
Vitalii Pertsevyi ◽  
Oleksandr Zhevzhyk ◽  
Iryna Potapchuk ◽  
Oleksandr Lutai

Analysis of the perspectives of the coal fuel for thermal power plants is carried out. The necessity of the experimental study for temperature measurement in the boiler furnace. The results of the experimental study are presented: temperature change over time at the burner outlet for different constant pressure value of the backlighting gas, dependence of the temperature at the burner outlet from the backlighting gas pressure for constant concentration value of pulverized coal in coal-air mixture, dependence of the temperature at the burner outlet from the concentration of pulverized coal in coal-air mixture for constant value of the backlighting gas pressure, temperature measurements for constant backlighting gas pressure value, constant value of the concentration of pulverized coal in coal-air mixture when plasmatron is switched and operates for some time range. The results of the study could be applied to the solid fuel treatment for different thermal units.


Author(s):  
Alireza Riasi ◽  
Ahmad Nourbakhsh

Unsteady flow analysis in water power stations is one of the most important issues in order to predict undesirable pressure variations in waterways and also probable changes in rotor speed for the power plants safe operation. Installation of surge tank and relief valve is the two main methods for controlling of hydraulic transient. The relief valve is used in several medium and small hydropower stations instead of the surge tank and mounted on the penstock near the powerhouse. The recent generation of relief valves are reliable and beneficial and consist of fully control system that directly conducted by governor. This paper presents a numerical method for transient flow in hydropower stations using surge tank and relief valve. For this purpose the governing equations of transient flow in closed conduit are solved using the method of characteristics (MOC) using unsteady friction. Hydraulic turbine, surge tank and relief valve are considered as internal boundary conditions. The influence of surge tank and also relief valve on the maximum pressure in spiral case and turbine over speed has been studied for a real case. The results show that the transient condition is considerably improved by using a relief valve and this device can be mounted in lieu of an expensive surge tank.


2021 ◽  
Author(s):  
Emmanuel Appiah ◽  
Phillip Wiseman

Abstract Integrity of a piping system is a prerequisite for personnel safety and operational reliability in industries where pipelines are critical means of transferring products from one process point to the other, such as power plants, refinery plants, and chemical industries. An essential aspect of designing a reliable piping system is to design supports of suitable load carrying capacity. This also depends on accurate determination of expected support loads including loads due to vibration of the system. Piping design codes such as ASME B31.3 and B31.1 provide a general framework but do not address vibration and its impact from a detailed perspective. In many situations, the potential impact of vibration is overlooked during support load determination. In recent piping system construction, the effect of vibration has increased due to increase in fluid flow rates and use of high strength thin wall materials. Common factors that contribute to vibration include: turbulent flow (flow induced vibration, FIV), relief valve operation (acoustic induced vibration, AIV), rotating and reciprocating equipment (pulsation induced vibrations, PIV). The effect of vibration depends on the strength of excitation and the flexibility of the piping system. As vibration of the piping system increases, loads transfer to the pipe supports also increase. Catastrophic failure of a piping system can occur if its natural frequency lock-in with the frequency of the excitation source. For holistic system integrity, the loads induced due to vibrations need to be accounted for in the support design. In this paper, we investigate the contributions of the various vibration loads in a piping system, the effect of neglecting the various vibration loads on the system integrity, and an empirical method to readily determine the vibration loads to reduce cost and time require in support design processes.


Author(s):  
Myron R. Anderson

Pressurized Water Reactor Power Plants have at times required that large components be replaced (steam generators weighing 750,000 lbs) which have necessitated performing first time modifications to the plant that were unintended during the original design. The steam generator replacement project at Tennessee Valley Authority (TVA’s) Sequoyah Nuclear Power Station necessitated (1) two large temporary openings (21’×45’) in the plant’s Shield Building roof (2’ thick concrete) by hydro-blasting to allow the removal of the old generators and installation of the new, (2) removal and repair of the concrete steam generator enclosure roofs (20’ diameter, 3’ thick) which were removed by wire saw cutting and (3) the seismic qualification of; the design and construction of an extensive ring foundation for; the use of one of the world largest cranes to remove these components through the roof. This removal and replacement process had to be performed in an expeditious manner to minimize the amount of time the plant is shutdown so the plant could return to providing power to the grid. This paper will address some of the many technical and construction considerations required to perform this demolition and repair work safely, efficiently and in a short as possible duration.


2013 ◽  
Vol 53 (1) ◽  
pp. 209
Author(s):  
Inge Alme ◽  
Angel Casal ◽  
Trygve Leinum ◽  
Helge Flesland

The BOP is a critical safety system of an offshore drilling rig, as shown in the 2010 Macondo accident. A challenge for the oil and gas industry is to decide what to do when the BOP is failing. Pulling the BOP to the surface during operations for inspection and testing is a costly and timely operation. Many of the potential failures are not critical to overall safety as multiple levels of redundancy are often available. Scandpower and Moduspec, both subsidiaries of Lloyd’s Register, have developed a BOP risk model that will assist the industry make the pull or no pull decisions. Scandpower’s proprietary software RiskSpectrum is used for the modelling. This software is used for equivalent decision support in the nuclear power industry, where the risk levels of total nuclear power plants are monitored live by operators in the control rooms. By modelling existing BOPs and their submerged control systems, and using risk monitor software for keeping track on the status of the BOP subsystems and components, the industry is able to define the real-time operational risk level the BOP is operating at. It, therefore, allows the inclusion for sensitivity modelling with possible faulty components factored in the model. The main task of the risk model is to guide and support energy companies and regulators in the decision process when considering whether to pull the BOP for repairs. Moreover, it will help the communication with the regulators, since the basis for the decisions are more traceable and easier to follow for a third party.


Author(s):  
Dan Wu ◽  
Jian Deng ◽  
Sijia Du ◽  
Libo Qian

Abstract In an over pressure accident, one or more pressurizer safety (or relief) valves will open due to the rapid pressure rise process. Once the safety (or relief) valves are open, the liquid seal will be discharged, and this will generate great discharge force to the downstream pipes. Multi-level protection is chosen using pressurizer safety (or relief) valves with different setpoint in most of Nuclear Power Plant, especially in the self-designed Generation-III Nuclear Power Plants. As the over pressure accident progresses, one or more safety (or relief) valves will be open. The downstream pipes will experience one or more times of impacts, which will influence the arrangement of the pipes. The whole discharge process is very complex, and the key influence factors are the pressure rise rate, safety (or relief) valve opening time, liquid seal temperature and volume, and the arrangement of the downstream discharge pipes. In present paper, liquid seal discharge process in an over pressure accident is studied. The pressure rise rate is so fast that three safety (or relief) valves will open one after another, which will generate three impacts on the downstream discharge pipes. It is found that for a specific design of Nuclear Power Plant, well design of the safety (or relief) valve setpoint is very important to the discharge force analysis results.


Author(s):  
Henry M. Stephens

This paper establishes an alternative approach for nondestructive examination (NDE) personnel qualification for the boiler and pressure vessel (B&PV) industry. This is the “white paper” developed by the Section XI, Division 2, Task Team, Performance-based NDE Personnel Qualifications. It is anticipated to be the basis for the NDE personnel qualification criteria for the revised Section XI, Division 2, REQUIREMENTS FOR RELIABILITY AND INTEGRITY MANAGEMENT (RIM) PROGRAM FOR NUCLEAR POWER PLANTS that is currently being developed. Based on review of a number of quantitative NDE reliability studies conducted to-date the current deterministic approach to NDE personnel qualification based on such schemes as ASNT SNT-TC-1A, ANSI/ASNT CP-189, EN-473, ISO-9712 and other similar approaches are not as effective as desired. The goal of this document is to present an alternative approach to the deterministic NDE personnel qualification schemes. This paper presents a systematic approach to training together with performance-based tests, psychometrically validated evaluation of knowledge and skills that will improve a NDE candidate’s performance. A majority of traditional employer-based written examinations are not developed or validated psychometrically. The use of third-party psychometrically validated examinations would replace the current practice of employer developed and administered examinations. It improves upon traditional ASNT SNT-TC-1A, ASNT/ANSI CP-189, ISO-9712, etc., requirements by including more comprehensive hands-on practical examinations on a statistically valid set of samples containing flaws representative of those expected to be encounter in shop and field conditions. The sample sets will be designed for either a “general” NDE method, or “limited” technique(s) of a method, or for industry specific sector needs, as applicable.


2010 ◽  
Vol 132 (5) ◽  
Author(s):  
David H. Creates

Fatigue evaluation in B31.1 is currently done based on equations 1 and 2 of ASME B31.1-2007 Power Piping, which only considers the displacement load ranges. However, fatigue damage, in addition to displacement load ranges, is occurring in B31.1 piping due to pressure cycling and thermal gradients. To exacerbate this, power plant design pressures and temperatures are rising, new materials are being introduced, pipes and attached components are becoming increasingly thick, and owners are requiring power plants to heat-up and cool-down at faster rates. Also, power plant owners are more and more interested in extending the life of power plants beyond their original design life. This article takes the first step in addressing the pressing need to address this additional fatigue damage by quantifying thermal gradients in the prevalent B31.1 welding end transitions in Fig. 127.4.2, or tapered transition joints (TTJs) in Appendix D, of ASME B31.1-2007 Power Piping by formulae to be able to evaluate their contribution to fatigue (see PVP2009-77148 [A Procedure to Evaluate a B31.1 Welding End Transition Joint to Include the Fatigue Effects of Thermal Gradients for Design and Plant Life Extension]). The disadvantage of this approach is that the conservatisms inherent in the calculations of thermal gradients, as per ASME Section III Subsection NB3600-2007, are also inherent in these calculations and may produce unacceptable results when evaluated as per PVP2009-77148 [A Procedure to Evaluate a B31.1 Welding End Transition Joint to Include the Fatigue Effects of Thermal Gradients for Design and Plant Life Extension]. If the results are unacceptable, it is a warning that something else needs to be done. The advantage of this approach is that it eliminates the need for a computer program to quantify these thermal gradients, a computer program that is not normally accessible to the B31.1 designer anyway. Instead, the formulae use the data that are available to the B31.1 designer, namely, physical geometry, thermal conductivity, and rate of temperature change in the fluid in the pipe. This will further help to preserve the integrity of the piping pressure boundary and, consequently, the safety of personnel in today’s power plants and into the future.


Sign in / Sign up

Export Citation Format

Share Document