Alternative Method of Buoy Supporting Riser (BSR) Installation

Author(s):  
Ricardo Franciss ◽  
Enrique Casaprima Gonzales ◽  
Jose´ Carlos Lima de Almeida ◽  
Jairo Bastos de Arau´jo ◽  
Antonio Carlos Fernandes

Due to the 2200m water depth and harsher environmental conditions, one option that Petrobras is considering for the production of the Pre-Salt fields is the use of a subsurface buoy known as a Buoy Supporting Riser (BSR). It is composed of a subsurface tethered buoy, flexible jumpers connecting the Floating Production Unit (FPU) to the BSR and Steel Catenary Risers (SCRs) connecting the BSR to the flowlines on the sea bottom. The main advantages of this system are that it decouples the FPU motions from the SCRs, reducing fatigue damage in the touch down zone. It may also be installed independently of the FPU, except for the flexible jumpers, which would reduce the risers load on the FPU. Petrobras has been studying this concept since 1997 and has established, as a final stage of the study, a field test with the actual installation of the BSR. This was performed through an alternative method using only Petrobras AHTS boats, in order to avoid critical and expensive resources such as lift barges. With the purpose of validating this new installation procedure, Petrobras performed the referred installation of a 27.2m × 27.2m square ring shaped buoy in Congro Field in the Campos Basin over a water depth of 500m. The buoy was positioned at 80m depth, where the incidence of loads caused by waves is negligible, thus increasing the fatigue life of risers. After the BSR installation, the riser pull-in procedure was also conduced. This paper describes why this technology is necessary for these fields and the model tests made to validate the installation procedures. It also discusses how Petrobras tested the pull-in operations for two flexible risers after the actual buoy was installed. Monitoring systems were designed to check all forces and displacements during the referred installation. These actions will consolidate the BSR technology for Petrobras leading to another riser system option for production in ultra deep waters.

Author(s):  
Ricardo Franciss ◽  
Elton Ribeiro

Petrobras is going deeper and some fields are feasible only if the production platforms are installed in ultra deep waters, close to the wells. In one case in Campos Basin, for example, the platform will be installed at 1255 m water depth and the solution to allow the production is based on the evolution of flexible lines for high pressure and high loads. For the oil export line, however, a steel rigid line was chosen, due to the large diameter. Some analyses were performed in order to make it feasible the installation of an 18-inch SCR export oil line. Due to fatigue loads, the free hanging catenary configuration did not match with API RP 2RD recommendations, so Petrobras decided to change the original shape to Lazy Wave in order to reduce the top loads and increase the fatigue life. But, some configurations are not feasible to install. High angles close to the installation vessel or high stresses close to the flotation segments are some problems that must be solved. This article will present the steps made to reach a configuration that will make feasible the installation of this riser, in parallel to the static and dynamic analysis, to maintain the stresses in an allowable level, in accordance with API RP 2RD.


Author(s):  
Jairo Bastos de Arau´jo ◽  
Jose´ Carlos Lima de Almeida ◽  
Antonio Carlos Fernandes

The BSR (Buoy for Supporting Risers) concept is composed by a submerged buoy anchored to the sea bottom by tethers and intended to support risers coming from the bottom (probably SCRs — Steel Catenary Risers) and going to the floating platform (probably with flexible jumpers). For the case under analysis here, the main dimensions of the BSR prototype are 27.2 m length × 27.2 m width × 5.0 m depth. The paper describes all final full scale installation step so that the BSR may be considered a suitable technology. The installation indeed was the great challenge of this design due the size of the hull. The present work also evaluates numerically and experimentally a specific new manner to install the BSR with the support of auxiliary mooring lines among with the four tethers connected to it. One of the installation premises was to make use of Anchor Handling Supply Vessels instead of Crane Vessels. After this numerical analysis, the work went on by performing model tests that simulates the operation in a deep water model basin using 1:40 scale. The model test anticipated several problems such as the chain stopper weakness in the operation and others as discussed in this paper. As a conclusion the work was devised the most important parameters during the system installation and suggested ways to improve the methodology. In November 2009 the BSR was installed in 500 m of water depth at Congro field location, Campos Basin, offshore Brazil. The tethers were adjusted in January 2010 and in March 2010 two risers were installed. Thenceforward the last edge of this knowledge was considered over passed.


Author(s):  
Ricardo Franciss ◽  
Anderson Barata Custódio

The P-25 platform is located at 575 m water depth in Campos Basin, offshore Brazil. In the time of its conversion (1996), its process plant was designed to use cold water streaming from the Antartic continent to cool its equipment, accessories and compressing gas plant for exportation. The uptake riser installed in 1997 is 330 m long, 24″ OD pipe, hanging from the pontoon and the cold water flowing through it enters a sea chest located next to the support. This fully rigid riser was recently asked to be replaced. This paper presents the stages of the reanalysis of this compliant structure under conditions of low cost, so that the platform continues to suck cold water. Because of the presence of the uptake riser, the platform does not have a cooling plant that would else request area and weight, two important items in an arrangement, besides the high cost involved. Within the scope of the analyses, the replacement of the material (originally steel) with offloading hoses is tried out, in search for weight savings and lower cost. These hoses were reinforced with steel cables and their behavior was checked. Some tests were performed to verify the mechanical strength of this material and vibrations by VIV that occur in this structure. Monitoring systems were designed to check all forces and displacements during the referred installation. These actions will consolidate the technology for Petrobras leading to another riser system option for production in ultra deep waters.


Author(s):  
Marcos V. Rodrigues ◽  
Caroline Ferraz ◽  
Danilo Machado L. da Silva ◽  
Bruna Nabuco

With new discoveries in the Brazilian Pre-Salt area, the oil industry is facing huge challenges for exploration in ultra-deep waters. The riser system, to be used for the oil transportation from seabed to the production unit, is one of them. The definition of riser configurations for ultra-deep waters is a real challenge. Problems have being identified for flexible risers, hybrid risers and steel catenary risers (SCR) configurations to comply with rules requirements and criteria in water depths of 2000m. The objective of this work is to present a study on the fatigue behavior of a Steel Catenary Riser in 1800m of water depth. One of the main challenges for SCRs in ultra-deep waters is the fatigue, due to platform 1st order motions, at the touch down zone (TDZ). A case study is presented for a Steel Catenary Riser connected to a semi-submersible platform. The influence of some design and analysis parameters is studied in order to evaluate their impact on the SCR fatigue life. The main parameters to be evaluated in this work are: The mesh refinement, in the global analysis, at the Touch Down Zone; The internal fluid density variation along the riser, and; The 1st order platform motions applied to the top of riser; In addition to the results of this paper, some highlights are presented for SCR analysis in similar conditions.


Author(s):  
Arne Ulrik Bindingsbo̸ ◽  
Arve Bjo̸rset

High Pressure and High Temperature wells together with harsh environmental conditions puts a tough challenge on the flowline and riser design. The flexible riser which has been the favorite choice for many field developments with subsea wells have several technical limitations. Large gas fields such as Ormen Lange require large bore export risers. Steel risers are the preferred solutions with respect to durability and cost. Unfortunately, it is difficult for steel risers to accommodate the vessel motions of a semi submersible or ship. Heave restricted vessels such as TLP or SPAR are used together with toptensioned risers and surface trees. Based on the limitations of flexible risers Hydro is pursuing extensive research on riser and floater technology. As part of this research program a study on the effect on riser design caused by reducing vessel motions. The main goal is to introduce steel catenary risers (SCR) on semi submersible platforms. The typical draft of a semi submersible production platform is 20–25 m. By reengineering the design of such a platform and increasing the draft from 21 m to 40 m the vessel motions were reduced significantly. Hence, an opening for novel riser solutions was made. ULS and FLS analyses for 10″ and 30″ SCR in 300 and 1000 m water depth were carried out. The key result is that the 10Prime; riser satisfies both the ULS and FLS requirement for both vessel drafts and water depth and the 30Prime; riser satisfies the both the ULS and FLS requirement for the 40 m vessel draft at 1000 m water depth.


Author(s):  
Elton J. B. Ribeiro ◽  
Edson L. Labanca ◽  
Roberto Alvim ◽  
Otavio Veras

This paper presents a methodology to analyze the risers interference connected to an FPSO, which is using turret moored system in shallow water. It is not feasible in shallow water to use riser free hanging catenary configurations, since there is not enough length in order to dissipate FPSO dynamic response due to wave action, which can cause riser damage at TDP. Furthermore, FPSO static offset is very large, around 30% of water depth, when it is compared with deep water, around 11–12% of water depth. In order to become feasible a large number of risers connected to a FPSO using a turret moored system in shallow water are needed to use compliant configurations, such as: lazy wave, pliant wave and Lazy S. As mentioned above risers compliant configurations are capable to avoid riser damage at TDP, but they present a large lateral motion. Thus, riser interference becomes a critical issue to be overcome. As the applicable standards and rules are not entirely prescriptive about this issue, the riser analyst usually have to adopt independent criteria, such as load cases, internal fluid density, hydrodynamic coefficient considering or not wake effect and clashing criteria (allowable, partially allowable or not). Therefore, the proposed methodology is very robust and was used at FEED studies for FPSO OSX-2/3, both belong to OGX, which are planning to install them at the ending of 2013 in Campos Basin, offshore Brazil.


Author(s):  
Carlos A. D. Lemos ◽  
Fernando J. M. Sousa ◽  
Jose´ R. M. Sousa

Some PETROBRAS fields are near mature now, around 15 years of production, and their production still important to the company portfolio, the possibility of extending the service life of these flexible risers becomes extremely attractive. This work addresses the re-evaluation of the fatigue life of old flexible risers aiming to extend their fatigue life at the same environment conditions or at new and less challenging ones. To fulfill this condition a special procedure is being applied to stretch the service life of the installed flexible risers, considering irregular wave analysis conditions, distributions of damage around the circumference and along the bend stiffener area and phase difference between tension and bending and in some cases a coupled analysis of the ship, mooring and risers systems. This kind of new fatigue procedure could also become of paramount importance to Petrobras to allow the design of conventional flexible risers for ultra deep waters.


Author(s):  
Enrico Torselletti ◽  
Luigino Vitali ◽  
Erik Levold ◽  
Kim J. Mo̸rk

The development of deep water gas fields using trunklines to carry the gas to the markets is sometime limited by the feasibility/economics of the construction phase. In particular there is a market for using S-lay vessels in water depth larger than 1000m. The S-lay feasibility depends on the applicable tension at the tensioner which is a function of water depth, stinger length and stinger curvature (for given stinger length by its curvature). This means that, without major vessel up-grading and to avoid too long stingers that are prone to damages caused by environmental loads, the application of larger stinger curvatures than presently allowed by current regulations/state of the art is needed. The work presented in this paper is a result of the project “Development of a Design Guideline for Submarine Pipeline Installation” sponsored by STATOIL and HYDRO. The technical activities are performed in co-operation by DNV, STATOIL and SNAMPROGETTI. The scope of the project is to produce a LRFD (Load Resistant Factor Design) design guideline to be used in the definition and application of design criteria for the laying phase e.g. to S and J-lay methods/equipment. The guideline covers D/t from 15 to 45 and applied strains over the overbend in excess of 0.5%. This paper addresses the failure modes relevant for combined high curvatures/strains, axial, external pressure and local forces due to roller over the stinger of an S-lay vessel and to sea bottom contacts, particularly: • Residual pipe ovality after laying, • Maximum strain and bending moment capacity. Analytical equations are proposed in accordance with DNV OS F101 philosophy and design format.


Author(s):  
Marcos Donato Ferreira ◽  
Mauro Costa de Oliveira ◽  
Rafaella Cristina Carvalho ◽  
Sergio Hamilton Sphaier

In the development of the mooring design of FPSOs in spread mooring system (SMS) configuration, it was observed that the utilization of asymmetric riser arrangement in deep waters might lead to an asymmetrical roll response of the FPSO. In particular, concentrating all riser connections on the portside, it could be observed that roll and heave coupling under the influence of the riser dynamics might lead to a much lower roll response associated with waves coming from portside than from the starboard direction. Simulations were carried using an in-house time domain simulator, where the ship hydrodynamic behavior was represented through the use of impulse response functions and the lines dynamic through the use of non-linear finite element method, using an explicit integration scheme and a lumped mass approach. Non-linear viscous effects could be easily associated to the ship and line velocities. Measured motion responses of an actual FPSO in operation in Campos Basin are compared with the computations.


Author(s):  
Jairo Bastos de Araujo ◽  
Roge´rio Diniz Machado ◽  
Cipriano Jose de Medeiros Junior

Petrobras developed a new kind of anchoring device known as Torpedo. This is a steel pile of appropriate weight and shape that is launched in a free fall procedure to be used as fixed anchoring point by any type of floating unit. There are two Torpedoes, T-43 and T-98 weighing 43 and 98 metric tons respectively. On October 2002 T-43 was tested offshore Brazil in Campos Basin. The successful results approved and certified by Bureau Veritas, and the need for a feasible anchoring system for new Petrobras Units in deep water fields of Campos Basin led to the development of a Torpedo with High Holding Power. Petrobras FPSO P-50, a VLCC that is being converted with a spread-mooring configuration will be installed in Albacora Leste field in the second semester of 2004. Its mooring analysis showed that the required holding power for the mooring system would be very high. Drag embedment anchors option would require four big Anchor Handling Vessels for anchor tensioning operations at 1400 m water depth. For this purpose T-98 was designed and its field tests were completed in April 2003. This paper discusses T-98 design, building, tests and ABS certification for FPSO P-50.


Sign in / Sign up

Export Citation Format

Share Document